CSF- 71
OSI 618
Welcome All Road @ Scarboro Road
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Bidding
NULL
The design project at Welcome All Road and Scarborough Road will include the addition of a circular single lane roundabout to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage with a typical section of 30-inch curb & gutter, streetlights, 2-ft of stamped concrete beauty strip, and 5' wide sidewalks. Streetlights will be added during construction
NULL
AEI
August, 2026
May, 2021
July. 2027
July. 2027
Sales Tax
$304,266
$195,192
$109,074
Green
Green
Active