CSF- 47
RS 402
Will Lee Pines
Tier 1
Maintenance and Safety Enhancements
TSPLOST
City of South Fulton
Completed
NULL
The roads (Fradon Court and Welcome All Terrace) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CWM
Not Applicable
Not Applicable
NULL
November, 2018
NULL
Sales Tax
$93,864
$87,148
$6,716
Red
Green