Oakley Industrial Boulevard Full-Depth Reclamation Project Phase II
Tier 1
Roadway Projects
TSPLOST
Fairburn
Completed
NULL
The work consists of full depth reclamation, asphalt paving and striping on Oakley Industrial Boulevard Road from the deceleration lane of the Solstice Apartment Complex to SR 74 as the base bid. In addition, (Add Alternate #1) Oakley Industrial Boulevard (from SR 74 to SR 92), (Add Alternate #2) Oakley Industrial Boulevard (from SR 92 to Fayetteville Road), (Add Alternate #4) Oakley Industrial Boulevard (from just west of Bohannon Road to Creekwood Road).
C.W.Matthews
Moreland Altobelli Associates, LLC
December, 2020
July, 2021
March, 2022
October, 2021
Sales Tax
$2,609,883
$1,191,210
$1,418,673
Green
Green
Active