FA- 15
25-004
Duncan Park Road, New Location Roadway Project
Tier 1
Roadway Projects
TSPLOST
Fairburn
Construction
NULL
Extension of Park Road to provide a secondary entrance/exit into Clarence Duncan Park. REBID IFB: November 12th, 2025 Bid Opening: December 19th, 2025; 18 bids received. Low bidder: Piedmont Paving, Inc. for $4,566,732.55 NTP: March 16th, 2026 All work associated with the Duncan Park Road Project to be completed within three hundred and sixty (360) calendar days of the NTP.
Piedmont Paving, Inc.
Southeastern Engineering, Inc.
November, 2025
March, 2026
May, 2027
March, 2027
Sales Tax
$722,685
$0
$722,685
Green
Green
Active