Project ID
CSS- 27
Local ID
TS167
Project Name
Brandon Mill Road - Marsh Creek to Lost Forest Dr. - Design
Tier
Tier 1
Project Type
Pedestrian and Bike Improvements
Initiatve Type
TSPLOST
City
Sandy Springs
Current Stage
Completed
Image File
Description
Connect the sidewalk system on east side of Brandon Mill Road from existing sidewalk to Lost Forest Dr
Construction Firm Selected
CMES
Design Firm Selected
Atkins
Estimated Design Completion Date
March, 2019
Estimated Start Date For Project
October, 2017
Estimated Construction Completion Date
March, 2022
Estimated Substantial Completion Date
March, 2022
Link To External Website
Primary Funding Source
Sales Tax
TSPLOST Budget ($)
$1,950,728
TSPLOST Dollars Spent ($)
$1,725,047
TSPLOST Dollars Committed (not spent) ($)
$225,681
Cost Status
Green
Schedule Status
Green
Status
Active
Editor
ajohnson@sandyspringsga.gov
Project Year
2022
Last Update
2024-10-18 16:02:43
State
NULL
Address
NULL
Creation Date
NULL
Back to list
Export
Export to Pdf
Export to Excel
Export to Word
Export to Xml
Export to Csv
Print
×
Change your password
Change password for user '
'
Current password
New password
Confirm password
Passwords do not match. Please try again.