CSS- 20
TS193
Hammond Drive - Phase 1 Efficiency Improvements
Tier 1
Congestion Relief
TSPLOST
Sandy Springs
Completed
The project limits are Hammond Drive from Roswell Road (State Route 9) to Glenridge Drive. The scope of work includes developing concepts for the widening of Hammond Drive with associated operational improvements to intersections along the corridor. The goals of this project are to improve safety, mobility, and improve pedestrian/bicycle access.
NULL
Gresham Smith
July, 2022
September, 2018
NULL
NULL
Sales Tax
$12,504,162
$12,504,162
$0
Green
Green
Active
ajohnson@sandyspringsga.gov
NULL
2023-12-14 15:56:19
NULL
NULL
NULL