FA- 3
17-005
Roadway Improvements on Various City Roads Project
Tier 1
Maintenance and Safety Enhancements
TSPLOST
Fairburn
Completed
NULL
City-Wide Resurfacing. The project includes milling, temporary traffic control, asphalt paving, thermoplastic striping, manhole adjustments and associated tasks. Our strategy was to use 2017-2018 TSPLOST funds to focus our resurfacing efforts on the heart of the City (downtown) and extend future efforts to its extremities. In doing so, the implementation of the Downtown LCI Project, would have a more meaningful impact on the revitalization of FairburnÆs Historic Downtown.
E.R. Snell Contractor, Inc.
In-House
June, 2017
November, 2017
December, 2018
October, 2018
Sales Tax
$1,200,000
$968,367
$231,633
Green
Green
Active
lthompson@fairburn.com
2017
NULL
NULL
NULL
NULL