EP- 4
EP-004
Ale Circle Realignment and Desert Drive N Extension
Tier 1
Operation and Safety Improvements
TSPLOST
East Point
Land
NULL
The project is in "Land Acquisition and Environmental Permitting" and the purpose of this project is to reduce traffic and safety issue at the intersection of Washington Road & Camp Creek Pkwy.
NULL
Lowe Engineers
June, 2018
January, 2022
November, 2022
November, 2022
Sales Tax
$1,850,000
$176,000
$1,674,000
Green
Red
Active
guest
2018
2021-10-11 22:05:54
NULL
NULL
NULL