ROS- 23
NULL
Cox Road Intersection Improvements (at Etris Rd and at King Rd)
Tier 1
Operation and Safety Improvements
TSPLOST2
Roswell
Concept
NULL
Project will construct new intersection improvements on Cox Road at both King Road and at Etris Road.. Per Agreement with City of Milton, Milton is lead on project
NULL
Pond
NULL
NULL
NULL
NULL
Sales Tax
$1,000,000
$0
$1,000,000
Green
Green
Active
dcox@roswellgov.com
NULL
2024-03-05 17:11:41
Georgia
Cox Road
2022-03-31