FA- 32
24-009
Gullatt Road Full-Depth Reclamation
Tier 1
Roadway Projects
TSPLOST2
Fairburn
Completed
NULL
"Full-Depth Reclamation of Gullatt Road from McLarin Road East to just west of Cleckler Road. The project also included asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. The approved T-SPLOST Project List allocates $$674,612.00 of Roadway Projects funding to the Full-Depth Reclamation of Gullatt Road. Total Project cost 2,658,412.08
BLOUNT CONSTRUCTION
SOUTHEASTERN ENGINEERING INC.
April, 2024
July, 2024
November, 2024
October, 2024
Sales Tax
$337,306
$674,612
$-337,306
Green
Green
Active
anthony.belcher@fairburn.com
2024
2025-08-04 16:36:16
Georgia
Gullatt Road
2022-03-31