FA- 27
25-004
City Wide Road Resurfacing
Tier 1
Roadway Projects
TSPLOST2
Fairburn
Construction
NULL
The City of Fairburn will accept sealed bids from qualified Contractors for furnishing all labor, equipment, and materials necessary to complete 4.1 mi of Roadway Improvements ON VARIOUS CITY ROADS Contract #25-004. The work includes milling, temporary traffic control, asphalt paving, manhole adjustments and associated tasks. The scope of Add Alternate #1 consists of the paving of the VETERANS OF FOREIGN WARS (VFW) parking lot located at 1699 Park Rd. Fairburn, GA 30213. All work must be completed within one hundred and twenty (120) calendar days of the Notice to Proceed (NTP).
TRIPLE R CONSTRUCTION
In-house
June, 2025
July, 2025
November, 2025
October, 2025
Sales Tax
$1,688,078
$0
$1,688,078
Green
Green
Active
anthony.belcher@fairburn.com
2025
2025-08-01 13:45:39
Georgia
City of Fairburn
2022-03-31