CH- 14
NULL
City Wide
Tier 3
Maintenance and Safety Enhancements
TSPLOST2
Chattahoochee Hills
Construction
NULL
deep patching on Rico Road (SFP to Hutcheson Ferry Road) utilizing 19mm asphalt, a 4” wide milling head at a depth of 4”, as well as 4” paint to repair existing striping damaged during construction
Piedmont Paving
Keck & Wood
August, 2024
May, 2024
August, 2024
August, 2024
$269,180 from TSPLOST & $1,500.000 from Capital
$1,769,180
$0
$1,769,180
Green
Green
Active
robbie.rokovitz@chatthillsga.us
2024
2024-04-23 16:38:59
Georgia
City of Chattahoochee Hills
2024-04-23