Project ID
ALP- 66
Local ID
C3001
Project Name
Roundabout (Hopewell Rd at Vaughan Dr)
Tier
Tier 3
Project Type
Operation and Safety Improvements
Initiatve Type
TSPLOST2
City
Alpharetta
Current Stage
Design
Image File
NULL
Description
Design of a roundabout at the intersection of Hopewell Road and Vaughan Drive was funded in FY 2020 and is complete. The roundabout would serve to assist in the following: denote one is entering into Alpharetta; aid in slowing traffic entering into the Downtown area; and assist in turning onto/off of Vaughan Drive. Since this project is a Tier 3 Project in the TSPLSOT Program, projects in Tier 1 are accomplished first prior to moving onto Tier 2 or 3 projects, unless there is a re-allocation of funds or revenue collected permits moving onto the other tiers.
Construction Firm Selected
Design Firm Selected
TBD
Estimated Design Completion Date
March, 2022
Estimated Start Date For Project
March, 2022
Estimated Construction Completion Date
Not Applicable
Estimated Substantial Completion Date
Not Applicable
Link To External Website
https://cleargov.com/georgia/fulton/city/alpharetta/projects/3810/roundabout:-hopewell-rd-at-vaughan-dr-(tsplost_2,-tier_3)
Primary Funding Source
Sales Tax
TSPLOST Budget ($)
$1,500,000
TSPLOST Dollars Spent ($)
$0
TSPLOST Dollars Committed (not spent) ($)
$1,500,000
Cost Status
Green
Schedule Status
Green
Status
Active
Editor
kmcdowell@alpharetta.ga.us
Project Year
2022
Last Update
2024-01-09 10:27:40
State
Georgia
Address
Hopewell Rd at Vaughan Dr
Creation Date
2022-03-31
Back to list
Export
Export to Pdf
Export to Excel
Export to Word
Export to Xml
Export to Csv
Print
×
Change your password
Change password for user '
'
Current password
New password
Confirm password
Passwords do not match. Please try again.