CSF- 111
RS 301
Beacon Hills
Tier 1
Maintenance and Safety Enhancements
TSPLOST
City of South Fulton
Completed
NULL
The roads (Berry Hill Court, Diann Court, Dianne Court, Dianne Drive, Green Trail, and Greentree Court) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews
Not Applicable
Not Applicable
NULL
November, 2021
NULL
Sales Tax
$124,513
$89,983
$34,530
Green
Green
Active
roussan.francois@fultoncountyga.gov
2021
2023-03-02 14:13:31
NULL
NULL
NULL