Actions Project ID Local ID Project Name Tier Project Type Initiatve Type City Current Stage Description Construction Firm Selected Design Firm Selected Estimated Design Completion Date Estimated Start Date For Project Estimated Construction Completion Date Estimated Substantial Completion Date Link To External Website Primary Funding Source TSPLOST Budget ($) TSPLOST Dollars Spent ($) TSPLOST Dollars Committed (not spent) ($) Cost Status Schedule Status Status Editor Project Year Last Update State Address Creation Date
CSF- 153 RS 343 Huntington Estates Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Fox Lane Drive, Fox Trail Drive, Hunters Forest Court, and Hunte... more
The roads (Fox Lane Drive, Fox Trail Drive, Hunters Forest Court, and Hunters Forest Lane) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
NULL Not Applicable Not Applicable NULL November, 2019 NULL Sales Tax $76,623 $160,756 $-84,133 Red Green Active roussan.francois@fultoncountyga.gov 2019 2021-05-03 19:39:42 NULL NULL NULL
CSF- 154 RS 344 Jamaica Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Montego Bay Drive and Port Antonio Court) within the subdivision... more
The roads (Montego Bay Drive and Port Antonio Court) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL November, 2020 NULL Sales Tax $116,851 $100,639 $16,212 Yellow Green Active roussan.francois@fultoncountyga.gov 2020 2023-03-02 13:49:44 NULL NULL NULL
CSF- 155 RS 345 Kensington Woods Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The road (Kenwood Trail) within the subdivision to be resurfaced may have e... more
The road (Kenwood Trail) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL November, 2021 NULL Sales Tax $53,636 $31,866 $21,770 Green Green Active roussan.francois@fultoncountyga.gov 2020 2023-03-02 13:50:26 NULL NULL NULL
CSF- 156 RS 346 Kimberly Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Bellburn Road, Birling Drive, Cadiz Circle, Cadiz Lane North, Ca... more
The roads (Bellburn Road, Birling Drive, Cadiz Circle, Cadiz Lane North, Cadiz Lane South, Glace Road, Keenan Court West, Keenan Lane, Keenan Road, Kimberly Mill Road, Piney Fork Lane, and Valleybend Lane) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CWM Not Applicable Not Applicable NULL June, 2019 NULL Sales Tax $840,941 $533,321 $307,620 Green Green Active roussan.francois@fultoncountyga.gov 2018 2021-05-03 19:41:25 NULL NULL NULL
CSF- 157 RS 347 Kimberly Forest Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Kimberly Creek Place, Kimberly Forest Way, and Onyx Court) withi... more
The roads (Kimberly Creek Place, Kimberly Forest Way, and Onyx Court) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CWM Not Applicable Not Applicable NULL June, 2018 NULL Sales Tax $76,623 $39,346 $37,277 Green Green Inactive roussan.francois@fultoncountyga.gov 2018 2021-02-06 23:46:48 NULL NULL NULL
CSF- 158 RS 348 Kings Crest Court Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The road (Kings Crest) within the subdivision to be resurfaced may have eit... more
The road (Kings Crest) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL November, 2020 NULL Sales Tax $24,903 $0 $24,903 Green Green Inactive roussan.francois@fultoncountyga.gov 2019 2023-03-02 13:51:06 NULL NULL NULL
CSF- 159 RS 349 Kings Ridge Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The road (Kings Crest Court) within the subdivision to be resurfaced may ha... more
The road (Kings Crest Court) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CWM Not Applicable Not Applicable NULL May, 2019 NULL Sales Tax $38,312 $327,732 $-289,420 Red Green Active roussan.francois@fultoncountyga.gov 2018 2021-05-03 19:45:38 NULL NULL NULL
CSF- 16 RS 373 Pointe Verda Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Case Domain Court, Lynfield Court, Lynfield Drive, and Pontevedr... more
The roads (Case Domain Court, Lynfield Court, Lynfield Drive, and Pontevedra Place) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL November, 2020 NULL Sales Tax $109,188 $384,653 $-275,465 Green Green Active roussan.francois@fultoncountyga.gov NULL 2023-03-02 14:08:47 NULL NULL NULL
CSF- 160 RS 350 Lake Feldwood Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Pebble Beach Court, Pebble Beach Drive, Tate Road, and Vernier D... more
The roads (Pebble Beach Court, Pebble Beach Drive, Tate Road, and Vernier Drive) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CWM Not Applicable November, 2018 NULL NULL NULL Sales Tax $132,175 $177,660 $-45,485 Red Green Active roussan.francois@fultoncountyga.gov 2018 2021-05-03 19:45:54 NULL NULL NULL
CSF- 161 RS 351 Lake Royale Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Kings Place, Lake Royale Drive, Lake Royale Place, Marla Circle,... more
The roads (Kings Place, Lake Royale Drive, Lake Royale Place, Marla Circle, Queens Court, Royal Lane, Royale Court, Royale Lane, and Sylvia Court) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL June, 2021 NULL Sales Tax $304,578 $164,673 $139,905 Green Green Active roussan.francois@fultoncountyga.gov 2020 2023-03-02 13:51:32 NULL NULL NULL
CSF- 162 RS 352 Lattimore Park Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The road (Buffington Drive) within the subdivision to be resurfaced may hav... more
The road (Buffington Drive) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
NULL Not Applicable Not Applicable NULL November, 2020 NULL Sales Tax $53,636 $174,195 $-120,559 Red Green Active roussan.francois@fultoncountyga.gov 2019 2021-05-03 19:47:08 NULL NULL NULL
CSF- 163 RS 353 Marion Woods Estates Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Cascade Overlook, Ellen Place, and Louise Terrace) within the su... more
The roads (Cascade Overlook, Ellen Place, and Louise Terrace) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL November, 2020 NULL Sales Tax $65,130 $81,957 $-16,827 Green Green Active roussan.francois@fultoncountyga.gov 2020 2023-03-02 13:52:01 NULL NULL NULL
CSF- 164 RS 354 Melanie Manor Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The road (Melanie Way) wihin the subdivision to be resurfaced may have eith... more
The road (Melanie Way) wihin the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
NULL Not Applicable Not Applicable NULL November, 2019 NULL Sales Tax $19,156 $190,980 $-171,824 Red Green Active roussan.francois@fultoncountyga.gov 2019 2021-05-03 19:48:28 NULL NULL NULL
CSF- 165 RS 355 Melanie Woods Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Hodge Drive and Melanie Woods Drive) within the subdivision to b... more
The roads (Hodge Drive and Melanie Woods Drive) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
NULL Not Applicable Not Applicable NULL November, 2020 NULL Sales Tax $26,818 $104,604 $-77,786 Red Green Active roussan.francois@fultoncountyga.gov 2019 2021-05-03 19:49:01 NULL NULL NULL
CSF- 166 RS 356 Milam Manor Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Autumn Green Drive, Bradley Court, and Garvey Drive II) within t... more
The roads (Autumn Green Drive, Bradley Court, and Garvey Drive II) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL August, 2021 NULL Sales Tax $105,357 $70,629 $34,728 Green Green Active roussan.francois@fultoncountyga.gov 2021 2023-03-02 14:19:37 NULL NULL NULL
CSF- 167 RS 357 Milam Park Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Planning The roads (Milam Loop and Milam Way) within the subdivision to be resurface... more
The roads (Milam Loop and Milam Way) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
NULL Not Applicable Not Applicable NULL November, 2019 NULL Sales Tax $128,344 $0 $128,344 Green Green Inactive roussan.francois@fultoncountyga.gov 2019 2021-05-03 19:50:53 NULL NULL NULL
CSF- 168 RS 358 Mitchell Crossing Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The road (Mitchell Crossing Drive) within the subdivision to be resurfaced ... more
The road (Mitchell Crossing Drive) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CWM Not Applicable Not Applicable NULL November, 2019 NULL Sales Tax $36,396 $30,064 $6,332 Green Green Active roussan.francois@fultoncountyga.gov 2018 2021-05-03 19:51:34 NULL NULL NULL
CSF- 169 RS 359 Montclair Estates Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Bellecour Court, Bordeaux Court, Collines Avenue, Collines Court... more
The roads (Bellecour Court, Bordeaux Court, Collines Avenue, Collines Court, Colonade Avenue, Esprit Court, Lyon Avenue, Lyon Court, Montague Avenue, and Montcalm Drive) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL November, 2020 NULL Sales Tax $348,636 $278,761 $69,875 Green Green Active roussan.francois@fultoncountyga.gov 2020 2023-03-02 13:52:46 NULL NULL NULL
CSF- 17 RS 374 Pointer Ridge Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Ashdale Drive, Basswood Court, Buckhurst Drive, Buckhurst Trail,... more
The roads (Ashdale Drive, Basswood Court, Buckhurst Drive, Buckhurst Trail, Buckhurst Way, Cedar Hurst Court, Cedar Hurst Trail, Cedar Hurst Way, Connell Road, Foxlair Drive, Foxlair Trail, Hidden Brook Court, Hidden Brook Trail, Hurst Point, Leisure Court, Leisure Lane, Leisure Trail, Medway Court, Pointer Court, Rockfort Court, Rockfort Drive, and Woodford Road) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CW Matthews Not Applicable Not Applicable NULL July, 2020 NULL Sales Tax $1,879,188 $1,364,734 $514,454 Green Green Active roussan.francois@fultoncountyga.gov 2019 2021-05-03 20:02:29 NULL NULL NULL
CSF- 170 RS 360 Monterey Tier 1 Maintenance and Safety Enhancements TSPLOST City of South Fulton Completed The roads (Barcelona Court, Cadera Court, Carriage Court ll, Cocina Court, ... more
The roads (Barcelona Court, Cadera Court, Carriage Court ll, Cocina Court, Crestwood Circle, Lantern Lane I, Old Carriage Drive II, and Old Spanish Trail) within the subdivsion to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
CWM Not Applicable Not Applicable NULL July, 2019 NULL Sales Tax $346,721 $271,513 $75,208 Green Green Active roussan.francois@fultoncountyga.gov 2018 2021-05-03 19:52:59 NULL NULL NULL
SUM = 193,906,703 SUM = 142,040,425,058 SUM = -141,846,518,355