Here you can select the number of cards to be placed in a row for each of supported screen resolutions. Your current resolution is highlighted in this way.
Lake Forrest Drive (Mt. Paran Road to Long Island Drive)
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Sandy Springs
Design
Lake Forrest Drive (Mt. Paran Road to Long Island Drive)
NULL
Kimley Horn
NULL
January, 2023
NULL
NULL
Sales Tax
$790,000
$0
$790,000
Green
NULL
Inactive
ajohnson@sandyspringsga.gov
NULL
2024-07-22 13:48:25
NULL
5060 Lake Forrest Dr NW, Sandy Springs, GA 30342
NULL
CSS- 67
S2184
Jett Ferry Road/Spalding Drive (Jett Ferry Court to Dunvegan Close)
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Sandy Springs
Construction
Jett Ferry Road/Spalding Drive (Jett Ferry Court to Dunvegan Close)
Sol Construction
Kimley Horn
June, 2026
December, 2021
September, 2026
September, 2026
Sales Tax
$700,000
$148,431
$551,569
Green
Green
Active
ajohnson@sandyspringsga.gov
2026
2026-03-06 15:44:03
NULL
3245 Spalding Dr, Sandy Springs, GA 30350
NULL
CSS- 68
S2171
Dalrymple Road (Duncourtney to Glencourtney Drive to 605 Dalrymple Road)
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Sandy Springs
Planning
Dalrymple Road (Duncourtney to Glencourtney Drive to 605 Dalrymple Road)
NULL
NULL
NULL
NULL
NULL
NULL
Sales Tax
$0
$0
$0
Green
NULL
Active
ajohnson@sandyspringsga.gov
NULL
2024-05-20 14:50:43
NULL
471 Dalrymple Rd, Sandy Springs, GA 30328
NULL
CSS- 69
S2174
Long Island Drive @ 5910 Gap Fill
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Sandy Springs
Planning
Long Island Drive @ 5910 Gap Fill
NULL
NULL
NULL
NULL
NULL
NULL
Sales Tax
$0
$0
$0
Green
NULL
Active
ajohnson@sandyspringsga.gov
NULL
2024-05-20 14:51:28
NULL
5910 Long Island Dr, Sandy Springs, GA 30328
NULL
CSS- 7
TS109
Peachtree-Dunwoody Road at Windsor Parkway
Tier 1
Operation and Safety Improvements
TSPLOST
Sandy Springs
Completed
Add and extend SB left-turn lane and WB right-turn lane
NULL
Clark Patterson Lee
February, 2021
August, 2018
September, 2021
August, 2021
Sales Tax
$0
$0
$0
Green
Green
Inactive
ajohnson@sandyspringsga.gov
2021
2022-05-26 17:54:22
NULL
NULL
NULL
CSS- 70
S2169
Carpenter Drive @ 345 Carpenter Dr
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Sandy Springs
Planning
Carpenter Drive @ 345 Carpenter Dr
NULL
NULL
NULL
December, 2022
NULL
NULL
Sales Tax
$0
$0
$0
Green
NULL
Active
ajohnson@sandyspringsga.gov
NULL
2024-05-20 14:49:38
NULL
345 Carpenter Dr NE,Sandy Springs, GA 30328
NULL
CSS- 71
S2188-2
South Johnson Ferry Road at Brookhaven City Limit
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Sandy Springs
Completed
This project will add a sidewalk and sidewalk ramp at the northeast corner ... more
This project will add a sidewalk and sidewalk ramp at the northeast corner of the intersection and a sidewalk extension with ramp on along the south side of Allen Road that will connect to the existing crosswalk across Allen Road.Â
Blount Construction
NV5
NULL
January, 2023
November, 2023
November, 2023
Sales Tax
$65,000
$254,017
$-189,017
NULL
NULL
Active
ajohnson@sandyspringsga.gov
2023
2026-03-06 15:44:54
NULL
1531 Johnson Ferry Rd NE, Sandy Springs, GA 30319
NULL
CSS- 72
S2188-3
Glenridge Drive at Messina Way
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Sandy Springs
Completed
This sidewalk will provide a connection between the existing sidewalk at Sp... more
This sidewalk will provide a connection between the existing sidewalk at Spalding Trace to Messina Way
Blount Construction
NV5
NULL
January, 2023
March, 2024
March, 2024
Sales Tax
$65,000
$19,225
$45,775
Green
NULL
Active
ajohnson@sandyspringsga.gov
2024
2024-03-29 14:20:18
NULL
7001 Glenridge Dr, Sandy Springs, GA 30328
NULL
CSS- 73
S2188-4
River Exchange Drive Sidewalk
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Sandy Springs
Completed
The project will add 10'-wide sidepath along the west side of River Exchang... more
The project will add 10'-wide sidepath along the west side of River Exchange Dr. from Spalding Dr. North to the entrance of Crooked Creek Park. The project will also provide 6'-wide sidewalk from the entrance of Crooked Creek Park north to tie into existing sidewalk.