Roadway Improvements on Various City Roads Project
Tier 1
Maintenance and Safety Enhancements
TSPLOST
Fairburn
Completed
City-Wide Resurfacing. The project includes milling, temporary traffic cont... more
City-Wide Resurfacing. The project includes milling, temporary traffic control, asphalt paving, thermoplastic striping, manhole adjustments and associated tasks.
Our strategy was to use 2017-2018 TSPLOST funds to focus our resurfacing efforts on the heart of the City (downtown) and extend future efforts to its extremities. In doing so, the implementation of the Downtown LCI Project, would have a more meaningful impact on the revitalization of FairburnÆs Historic Downtown.
E.R. Snell Contractor, Inc.
In-House
June, 2017
November, 2017
December, 2018
October, 2018
Sales Tax
$1,200,000
$968,367
$231,633
Green
Green
Active
lthompson@fairburn.com
2017
NULL
NULL
NULL
NULL
FA- 30
25-011
Oakley Industrial Boulevard Left Turn Lane Project
Tier 3
Congestion Relief
TSPLOST2
Fairburn
Construction
The project consists of a total of 0.299 miles of widening to install a lef... more
The project consists of a total of 0.299 miles of widening to install a left turn lane along Oakley Industrial Boulevard at entrance of the SC Johnson's Distribution Center.
The budget impact will be $1,315,247.57. Of which, $1,065,807.57 will be reimbursed by the South Fulton Community Improvement District (CID) through an Intergovernmental Agreement (IGA). Thereby reducing the overall TSPLOST budget impact to $249,440.
The Notice to Proceed (NTP) with Construction was September 29th, 2025. The project is currently behind schedule due to significant utility conflicts and inclement weather.
• City of Fairburn Power relocations and switchover complete as of April 16, 2026.
• Comcast completed their utility relocation work that conflicted with the project proposed grading.
• Time extension of 150 calendar days approved on 2/17/2026 due to delays with utility conflicts.
• 20 days from 7/22/2026 – 8/19/2026 lost due to rain / wet conditions and utility relocations.
• AT&T continuing utility relocation work. Bores have been done, but the handholes have not been set due to awaiting splicing. Section cuts and out-of-service cuts are currently being arranged. This work was originally scheduled to be completed 8/7, but now fiber splicing is scheduled to be completed by 8/21. Once splicing has completed, handholes will be reset.
• Plans for the following month consist of Piedmont Paving finishing water main installation, side drain installation, and grading for roadway extension. This work is dependent upon AT&T completing their utility work
McLarin Road/E. Broad Street (Bohannon Road to Gullat Road) Full-Depth Recl... more
McLarin Road/E. Broad Street (Bohannon Road to Gullat Road) Full-Depth Reclamation
Tier 1
Roadway Projects
TSPLOST2
Fairburn
Completed
Full-Depth Reclamation of McLarin Road along with asphalt paving, the insta... more
Full-Depth Reclamation of McLarin Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments. From Bohannon Rd. to Gullatt Road.
BLOUNT CONSTRUCTION
SOUTHEASTERN ENGINEERING INC.
NULL
NULL
NULL
NULL
Sales Tax
$100,000
$100,000
$0
Green
NULL
Active
lthompson@fairburn.com
2024
2026-08-31 11:56:48
Georgia
McLarin Road
2022-03-31
FA- 32
24-009
Gullatt Road Full-Depth Reclamation
Tier 1
Roadway Projects
TSPLOST2
Fairburn
Completed
"Full-Depth Reclamation of Gullatt Road from McLarin Road East to just west... more
"Full-Depth Reclamation of Gullatt Road from McLarin Road East to just west of Cleckler Road. The project also included asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments.
The approved T-SPLOST Project List allocates $$674,612.00
of Roadway Projects funding to the Full-Depth Reclamation of Gullatt Road. Total Project cost 2,658,412.08
BLOUNT CONSTRUCTION
SOUTHEASTERN ENGINEERING INC.
April, 2024
July, 2024
November, 2024
October, 2024
Sales Tax
$337,306
$674,612
$-337,306
Green
Green
Active
anthony.belcher@fairburn.com
2024
2025-08-04 16:36:16
Georgia
Gullatt Road
2022-03-31
FA- 33
NULL
Quiet Zone R/R Crossings
Tier 2
Operation and Safety Improvements
TSPLOST2
Fairburn
Planning
NULL
NULL
NULL
NULL
NULL
NULL
NULL
Sales Tax
NULL
NULL
$0
NULL
NULL
Active
NULL
NULL
NULL
Georgia
City of Fairburn
2022-03-31
FA- 34
23-002
Pedestrian and Bike Improvements (Phase 2)
Tier 2
Pedestrian and Bike Improvements
TSPLOST2
Fairburn
Completed
SOUTHEAST BROAD STREET PEDESTRIAN IMPROVEMENTS PROJECT #23-002. The work in... more
SOUTHEAST BROAD STREET PEDESTRIAN IMPROVEMENTS PROJECT #23-002. The work includes the removal of existing curb & gutter, sidewalk and driveway aprons as required, installation of new curb & gutter, installation of new sidewalk, replacement of existing sidewalk as required, installation of new driveway aprons, and the installation of new ADA handicap ramps. The contract will also include preparation of sub-grade, saw-cutting and demolition of existing asphalt and concrete, as well as clean up and backfilling.
The extension of Oakley Industrial Boulevard, from Creekwood Road to Gullat... more
The extension of Oakley Industrial Boulevard, from Creekwood Road to Gullatt Road.
The project design is approximately 90% complete. The South Fulton Community Improvement District (CID) is covering the project's design costs.
The City of Fairburn expended approximately $15,823 in TSPLOST Funds on a Task Order with Atlas Technical Consultants for roadway staking and subsurface exploration to investigate the soil conditions for excavation purposes at the proposed Oakley Industrial Boulevard Extension between stations 104+00, 105+00, 108+00, 109+00, 110+00, and 111+00.
The project is currently in the ROW Acquisition Phase. There is a total of nine (9) parcels, with five (5) parcels remaining. This phase is holding up the project due to a stalemate in negotiations, making it significantly behind schedule.
The most recent rough construction cost estimate is $4,950,000.00 as of 1/22/2026.
NULL
SOUTHEASTERN ENGINEERING INC.
March, 2027
October, 2027
December, 2028
October, 2028
Sales Tax
$0
$15,823
$-15,823
Green
Red
Active
lthompson@fairburn.com
NULL
2026-08-31 11:46:25
Georgia
Oakley Industrial Boulevard
2022-03-31
FA- 4
17-004
Pedestrian Improvements on Various City Roads Project
Tier 1
Pedestrian and Bike Improvements
TSPLOST
Fairburn
Completed
The project includes grading complete, temporary traffic control, installat... more
The project includes grading complete, temporary traffic control, installation of sidewalk, driveway reconstruction, installation of handicap ramps, curb & gutter installation, header curb installation and associated tasks.
The is the first TSPLOST Pedestrian and Bike Improvements Project. The objective was to install new sidewalk and handicap ramps at various locations throughout the City that were currently not served with pedestrian facilities. The project also proposed connection to existing pedestrian facilities in the area. The project's purpose was to improve safety by providing a safe means for pedestrian to walk downtown to access various services and amenities. The project also provided pedestrians a safe means by which access to the newly renovated Clarence Duncan Memorial Park.
TOPLE Construction & Engineering
In-House
July, 2017
November, 2017
November, 2018
November, 2018
Sales Tax
$439,288
$193,565
$245,723
Green
Green
Active
lthompson@fairburn.com
2017
NULL
NULL
NULL
NULL
FA- 40
25-003
MULLIS STREET PEDESTRIAN IMPROVEMENTS PROJECT
Tier 1
Pedestrian and Bike Improvements
TSPLOST2
Fairburn
Construction
The installation of a 5-foot concrete sidewalk with a 2-foot beauty strip a... more
The installation of a 5-foot concrete sidewalk with a 2-foot beauty strip along Mullis Street, from West Campbellton Street to Dodd Street, and from Dodd Street to Strickland Street. The project also entails the installation of pedestrian improvements on a section of Dodd Street, from Mullis Street to W. Broad Street. The work includes the removal of existing curb & gutter and header curb, and the installation of new header curb and sidewalk. This contract will also include preparation of sub-grade, saw-cutting and demolition of existing asphalt as well as clean up and backfilling. The scope of Add Alternate #1 consists of the installation of pedestrian lighting
CONSTRUCTION 57 INC.
POND ENGINEERING
March, 2025
May, 2025
July, 2025
June, 2025
Sales Tax
$570,201
$570,201
$0
Green
Green
Active
anthony.belcher@fairburn.com
2025
2025-05-06 10:21:42
GA
NULL
2025-05-06
FA- 41
24-009
Cleckler Rd Full-Depth Reclamation Project
Tier 1
Maintenance and Safety Enhancements
TSPLOST2
Fairburn
Completed
Full-Depth Reclamation of Cleckler Road along with asphalt paving, the inst... more
Full-Depth Reclamation of Cleckler Road along with asphalt paving, the installation of thermoplastic striping and raised pavement markers (RPMs), and manhole and water valve adjustments.
The total project costs were $445,687.77. The South Fulton CID covered first $209,041.09 in construction costs, the remaining $236,646.68 in construction costs was paid for with TSPLOST Funds.
BLOUNT CONSTRUCTION
SOUTHEASTERN ENGINEERING INC.
May, 2024
July, 2024
November, 2024
October, 2024
Sales Tax
$209,041
$239,647
$-30,606
Green
Green
Active
lthompson@fairburn.com
2024
2026-08-31 11:55:35
GA
Cleckler Rd.
2025-05-06
FA- 42
25-011
Oakley Industrial Boulevard Left Turn Lane Project
Tier 1
Roadway Projects
TSPLOST2
Fairburn
Bidding
This project consists of a total of 0.299 miles of Widening on Oakley Indus... more
This project consists of a total of 0.299 miles of Widening on Oakley Industrial Boulevard at the entrance of SC Johnson's distribution center.
Brooks Drive Extension Roadway Project is to extend Brooks Drive from Fishe... more
Brooks Drive Extension Roadway Project is to extend Brooks Drive from Fisher Street to the dead end, west of the New Beginning Senior Center. The design also includes the widening and reconstruction of Brooks Drive, from Washington Street to the dead end.
The Task Order for $272,400 with Atlas Technical Consultants to Design the Brooks Drive Extension Roadway Project was approved at the March 25th, 2024, City Council Meeting.
The project is currently in the Right-of-Way (ROW) Acquisition Phase. As of August 24th, 2026, an agreement has been reached on 14 of the 22 parcels.
To date $272,372.23 has been spent on design services; $131,334.69 has been spend on ROW acquisition services; and $87,224.00 spent on the required ROW and easements or approximately $490,930.92.
NULL
Atlas Technical Consultants
April, 2027
NULL
NULL
NULL
Sales Tax
$1,500,000
$490,931
$1,009,069
Green
Green
Active
lthompson@fairburn.com
2025
2026-08-26 15:52:52
NULL
NULL
2025-07-31
FA- 44
23-003
Rivertown Connector Project
Tier 1
Roadway Projects
TSPLOST
Fairburn
Planning
City of Fairburn Roadway Project design to provide connectivity between Riv... more
City of Fairburn Roadway Project design to provide connectivity between Rivertown Road and Virlyn B. Smith Road.
NULL
SOUTHEASTERN ENGINEERING INC.
April, 2025
May, 2025
August, 2025
July, 2025
Sales Tax
$937,240
$0
$937,240
Gray
Gray
Inactive
anthony.belcher@fairburn.com
2020
2025-05-01 11:30:19
NULL
NULL
NULL
FA- 45
NULL
White Mill Road Full-Depth Reclamation
Tier 1
Maintenance and Safety Enhancements
TSPLOST2
Fairburn
Completed
The Full-Depth Reclamation of White Mill Road from SR 92 (Campbellton-Fairb... more
The Full-Depth Reclamation of White Mill Road from SR 92 (Campbellton-Fairburn Road) to Rivertown Road, which is mostly with the City of South Fulton and partially inside the City of Fairburn.
Through an IGA the City of South Fulton covered $1,270,558.31, and the City of Fairburn covered 158,400.
Atlanta Paving & Concrete Construction, Inc.
NULL
NULL
January, 2023
June, 2023
NULL
Sales Tax
$816,700
$158,400
$658,300
Green
Green
Active
lthompson@fairburn.com
2023
2026-08-31 11:57:27
NULL
NULL
NULL
FA- 46
26-004
Roadway Improvements on Various City Roads
Tier 1
Maintenance and Safety Enhancements
TSPLOST2
Fairburn
Construction
The Project was put out to bid April 22, 2026. The Bid Opening date was May... more
The Project was put out to bid April 22, 2026. The Bid Opening date was May 22, 2026
The Contract Award to Shepco Paving, Inc. for the Roadway Improvements on Various City Roads Project for the bid amount of $2,008,660.20 was approved by Mayor & Council at the June 8, 2026, City Council Meeting. The Notice of Award was issued to Shepco Paving, Inc. on June 10th, 2026. The Notice to Proceed (NTP) with Construction Date was July 13th, 2026.
In this year's City-Wide Resurfacing Project approximately ten (10) centerline miles of roadway, which includes eight (8) residential subdivisions will be resurfaced.
The City of Fairburn will combine Grant Funding and TSPLOST Funding to deliver this project to take advantage of the economies of scale. In doing so, the first $253,421.47 in project expenditures will be covered by an LMIG Grant from the Georgia Department of Transportation (GDOT); and the second $276,464.46 in project expenditures will be covered by a Local Road Assistance Grant from GDOT, for a total of $529,885.93 collectively to be covered by grants. The remaining project expenditures ($1,478,774.27) will be covered by TSPLOST Funds.
Prior to putting the project out to bid, the City of Fairburn requested fun... more
Prior to putting the project out to bid, the City of Fairburn requested funding assistance from the South Fulton CID to help deliver the Harris Road Full-Depth Reclamation Project. The CID agreed to pay $300,000 toward the construction of the project, with the understanding that Green Oil would cover the balance of the funding required to complete the construction. The agreement was subsequently formalized through an approves Intergovernmental Agreement (IGA).
Through an approved Memorandum of Understanding (MOU), Green Oil agreed to reimburse and provide upfront funding for the Project Advertisement, Preliminary Engineering and Design Services, Construction Management, Project Management, and the Construction Engineering and Inspection (CEI) Services costs associated with the Project for a total of $107,925 in total project funding.
The Invitation for Bid (IFB) for the Harris Road Full-Depth Reclamation Project was advertised on April 22nd, 2026. The bid opening date was May 22nd, 2026. The bid of the lowest responsive and responsible bidder came in at $369,725.75.
Mayor and Council approved the Contract Award to Blount Construction Company, Inc. for the Harris Road Full-Depth Reclamation Project for the bid amount of $369,725.75 at the July 13th, 2026, City Council Meeting.
The project entails full depth reclamation, asphalt paving and striping on Harris Road, from just west of Shortleaf Road (the Fairburn Family Travel Center Truck Stop exit) to the Senoia Road (SR74) Right-of-Way Limits. All work must be completed within sixty (60) calendar days of the Notice to Proceed with Construction (NTP).
The first ($300,000) in project expenditures will come out of account number (360-0000-54-1421) T-SPLOST Fund, SFCID – Harris Road FDR.
The remaining project expenditures ($69,725.75) will come out of account number (360-0000-52-1410) TSPLOST Fund, Infrastructure - Roadway.