Here you can select the number of cards to be placed in a row for each of supported screen resolutions. Your current resolution is highlighted in this way.
The roads (Appaloose Cove and Sorrel Drive) within the subdivision is to re... more
The roads (Appaloose Cove and Sorrel Drive) within the subdivision is to resurface the final asphalt topping layer. The roads within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work includes all necessary preparation work (e.g., full depth patching and a single surface treatment). The roads will then have the final asphalt topping layer installed in a manner that will provide uniformity of the asphalt. Milling of the existing asphalt surface is not expected to be required for these roadways.
E R Snell
Not Applicable
Not Applicable
March, 2018
August, 2018
Not Applicable
Sales Tax
$41,187
$39,476
$1,711
Green
Green
Active
roussan.francois@fultoncountyga.gov
2017
2021-05-03 20:30:42
NULL
NULL
NULL
CSF- 64
OSI 609
Feldwood Road @ Morning Creek Drive
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Completed
Intersection will be analyzed for traffic improvements including a roundabo... more
Intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will provide geometric and congestion relief.
NULL
AEI
December, 2022
NULL
January, 2023
NULL
Sales Tax
$952,800
$79,878
$872,922
Green
Green
Active
roussan.francois@fultoncountyga.gov
2021
2023-03-05 00:42:06
NULL
NULL
NULL
CSF- 65
OSI 610
Feldwood Road @ Bench Mark Drive
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Completed
Intersection will be analyzed for traffic improvements including a roundabo... more
Intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will provide geometric and congestion relief.
NULL
American Engineers, Inc
December, 2022
December, 2020
December, 2022
NULL
Sales Tax
$775,200
$35,000
$740,200
Green
Green
Active
roussan.francois@fultoncountyga.gov
2017
2023-03-05 00:45:19
NULL
NULL
NULL
CSF- 66
OSI 613/615
Old Fairburn Road @ Union Road
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Construction
The current construction project will include the addition of two circular ... more
The current construction project will include the addition of two circular roundabouts to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage, 24-inch curb & gutter, 24-inch stamp concrete beauty strip, streetlights, and 5' wide sidewalks. The extent of the project will extend approximately 500 feet each route direction from each roundabout. The roundabouts are approximately 900 feet apart. A 400 ft’ section of Old Fairburn Road will be removed as part of the realignment. Due to the proximity, this project is being delivered as a single construction project along with OSI 615 Stonewall Tell Road @ Union Road. Streetlights will also be added within the project limits
NULL
American Engineers, Inc
March, 2023
December, 2020
May, 2027
May, 2027
Sales Tax
$4,279,207
$1,446,683
$2,832,524
Green
Green
Active
roussan.francois@cityofsouthfultonga.gov
2017
2026-09-18 12:26:22
NULL
NULL
NULL
CSF- 67
OSI 614
Rivertown Road @ Cedar Grove Road
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Completed
This construction project at Rivertown Road and Cedar Grove Road will build... more
This construction project at Rivertown Road and Cedar Grove Road will build a single-lane roundabout to address a sharp angle intersection skew, congestion, and reduce the severity of accidents at this intersection. Additional improvements with this project include improving storm drainage with a typical section consisting of a 2-ft. curb & gutter, 2-ft. stamped concrete beauty strip, and 5-ft. wide sidewalks throughout the project limits. The extent of construction is approximately 1250 ft. along Rivertown Road and 600 ft. along Cedar Grove Road. Streetlights will also be added within the project limits.
Improvements will include the addition of a circular roundabout to address ... more
Improvements will include the addition of a circular roundabout to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage, curb & gutter, streetlights, and 5Æ wide sidewalks. Due to the proximity, this project will be delivered as a single construction project along with OSI 613 Old Fairburn Road at Union Road.
The design project at Jones Road, Stonewall tell Road and Pittman Road will... more
The design project at Jones Road, Stonewall tell Road and Pittman Road will include the addition of a circular single lane roundabout to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage, with a typical section of 30-inch curb & gutter, 2-ft of stamped concrete beauty strip, and 5' wide sidewalks. Streetlights will be added during construction.
NULL
AEI
November, 2024
December, 2020
January, 2028
January, 2028
Sales Tax
$314,294
$199,426
$114,868
Green
Green
Active
roussan.francois@cityofsouthfultonga.gov
2021
2026-09-18 13:37:49
NULL
NULL
NULL
CSF- 7
RC 106
New Hope Road (Boat Rock to Cascade Rd)
Tier 1
Maintenance and Safety Enhancements
TSPLOST
City of South Fulton
Completed
The New Hope Road (Boat Rock to Cascade Rd) to be resurfaced may have eithe... more
The New Hope Road (Boat Rock to Cascade Rd) to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
E R Snell
Not Applicable
Not Applicable
March, 2018
August, 2018
December, 2017
Sales Tax
$414,358
$453,951
$-39,593
Yellow
Green
Active
roussan.francois@fultoncountyga.gov
2017
2021-05-03 16:14:02
NULL
NULL
NULL
CSF- 70
OSI 617
Welcome All Road @ Jailette Road
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Bidding
The design project at Welcome All Road and Jailette Road will realign the S... more
The design project at Welcome All Road and Jailette Road will realign the Stop regulated approach of Jailette Road to improve the angle of incidence at the intersection with Welcome All. Additional improvements include drainage, with a typical section of 30-inch curb & gutter, 2-ft of stamped concrete beauty strip, and 5' wide sidewalks. Streetlights will be added during construction.
NULL
ATLAS
August, 2026
May, 2021
July. 2027
NULL
Sales Tax
$95,353
$75
$95,278
Green
Green
Active
roussan.francois@cityofsouthfultonga.gov
2020
2026-09-22 08:44:29
NULL
NULL
NULL
CSF- 71
OSI 618
Welcome All Road @ Scarboro Road
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Bidding
The design project at Welcome All Road and Scarborough Road will include th... more
The design project at Welcome All Road and Scarborough Road will include the addition of a circular single lane roundabout to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage with a typical section of 30-inch curb & gutter, streetlights, 2-ft of stamped concrete beauty strip, and 5' wide sidewalks. Streetlights will be added during construction
NULL
AEI
August, 2026
May, 2021
July. 2027
July. 2027
Sales Tax
$304,266
$195,192
$109,074
Green
Green
Active
roussan.francois@cityofsouthfultonga.gov
NULL
2026-09-22 08:46:47
NULL
NULL
NULL
CSF- 72
RST 202
Falls @ Camp Creek
Tier 1
Maintenance and Safety Enhancements
TSPLOST
City of South Fulton
Completed
The primary work is to resurface the final asphalt topping layer. The road ... more
The primary work is to resurface the final asphalt topping layer. The road Casa Blanca Lane) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work includes all necessary preparation work (e.g., full depth patching and a single surface treatment). The roads will then have the final asphalt topping layer installed in a manner that will provide uniformity of the asphalt. Milling of the existing asphalt surface is not expected to be required for these roadways.
E R Snell
Not Applicable
Not Applicable
March, 2018
August, 2018
Not Applicable
Sales Tax
$50,297
$62,067
$-11,770
Green
Green
Active
roussan.francois@fultoncountyga.gov
2017
2021-05-03 20:30:59
NULL
NULL
NULL
CSF- 73
OSI 619
West Stubbs Road @ Butner Road
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Design
The City of South Fulton is evaluating options to upgrade the intersection ... more
The City of South Fulton is evaluating options to upgrade the intersection of West Stubbs Road at Butner Road to improve safety and capacity throughout the project corridor. It will also provide pedestrian access and safety through the intersection area. Additional improvements include a closed drainage system, 2.5-ft. curb & gutter, 2' stamped concrete, and 5 ft. sidewalks. Streetlights (overhead and pedestrian scale) will be implemented near the end of the project.
NULL
NULL
NULL
July, 2021
NULL
NULL
Sales Tax
$47,326
$47,326
$0
Green
Green
Active
roussan.francois@cityofsouthfultonga.gov
2020
2026-09-22 08:56:25
NULL
NULL
NULL
CSF- 74
OSI 620
Aldredge Road @Merk Road
Tier 2
Operation and Safety Improvements
TSPLOST2
City of South Fulton
Design
improvements include three new turn lanes - a left on westbound Aldredge, a... more
improvements include three new turn lanes - a left on westbound Aldredge, and a right on eastbound Aldredge and a right on northbound Merk, a closed drainage system, 2.5-ft. curb & gutter, 2' stamped concrete, and 5 ft. sidewalks. Merk Road and Aldredge Road will be realigned to be a through street in the east-west direction and Merk Road from the south direction will be stop controlled.
NULL
NULL
February, 2027
July, 2021
October, 2028
October, 2030
Sales Tax
$207,130
$70,283
$136,847
Green
Green
Active
roussan.francois@cityofsouthfultonga.gov
NULL
2026-09-22 09:00:21
NULL
NULL
NULL
CSF- 75
OSI 621
Bethsaida Road @ Old National Hwy.
Tier 2
Operation and Safety Improvements
TSPLOST
City of South Fulton
Planning
Intersection will be analyzed for traffic improvements including a roundabo... more
Intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will provide geometric and congestion relief.
NULL
NULL
NULL
July, 2021
NULL
NULL
Sales Tax
$1,788,000
$0
$1,788,000
Gray
Gray
Active
NULL
NULL
NULL
NULL
NULL
NULL
CSF- 76
OSI 622
Butner Road @ Aldredge Road
Tier 2
Operation and Safety Improvements
TSPLOST
City of South Fulton
Planning
Intersection will be analyzed for traffic improvements including a roundabo... more
Intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will provide geometric and congestion relief.
NULL
NULL
NULL
July, 2021
NULL
NULL
Sales Tax
$1,434,000
$0
$1,434,000
Gray
Gray
Active
NULL
NULL
NULL
NULL
NULL
NULL
CSF- 77
OSI 624
Washington Road @ Roosevelt Highway
Tier 2
Operation and Safety Improvements
TSPLOST
City of South Fulton
Completed
Intersection will be analyzed for traffic improvements including a roundabo... more
Intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will provide geometric and congestion relief.
NULL
NULL
NULL
July, 2021
NULL
NULL
Sales Tax
$0
$0
$0
Gray
Gray
Active
roussan.francois@cityofsouthfultonga.gov
NULL
2026-09-22 09:07:07
NULL
NULL
NULL
CSF- 78
OSI 625
Welcome All Road @ Will Lee Road
Tier 2
Operation and Safety Improvements
TSPLOST
City of South Fulton
Planning
Intersection will be analyzed for traffic improvements including a roundabo... more
Intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will provide geometric and congestion relief.
NULL
NULL
July, 2021
NULL
NULL
NULL
Sales Tax
$0
$0
$0
Gray
Gray
Active
roussan.francois@cityofsouthfultonga.gov
NULL
2026-09-22 09:08:49
NULL
NULL
NULL
CSF- 79
SU 700
Flat Shoals Rd at Old National Hwy
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Design
Traffic signal upgrades will include new mast arm poles, new cabinets, dete... more
Traffic signal upgrades will include new mast arm poles, new cabinets, detection, signal heads, back plates, pedestrian signals, and pavement markings at the intersections. The work will include fiber communication along Flat Shoals Road from Mallory Road to Old National Highway.
NULL
Jacobs
March, 2023
September, 2020
July, 2024
NULL
Sales Tax
$250,000
$0
$250,000
Green
Green
Active
roussan.francois@fultoncountyga.gov
NULL
2023-03-06 12:54:47
NULL
NULL
NULL
CSF- 8
RC 107
Old Bill Cook Road (Buffington Rd to Old National Hwy)
Tier 1
Maintenance and Safety Enhancements
TSPLOST
City of South Fulton
Completed
The Old Bill Cook Road (Buffington Rd to Old National Hwy) to be resurfaced... more
The Old Bill Cook Road (Buffington Rd to Old National Hwy) to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
NULL
Not Applicable
Not Applicable
March, 2020
August, 2020
NULL
Sales Tax
$438,189
$458,162
$-19,973
Yellow
Green
Active
roussan.francois@fultoncountyga.gov
2019
2021-05-03 16:14:51
NULL
NULL
NULL
CSF- 80
SU 701
Flat Shoals Rd at Hemperly Rd
Tier 1
Operation and Safety Improvements
TSPLOST
City of South Fulton
Planning
The overall objective of this project is the redesign and reconstruction of... more
The overall objective of this project is the redesign and reconstruction of eleven (11) traffic signals along the Flat Shoals Road corridor to complement the proposed Advanced Traffic Management System (ATMS) along the corridor. Closed Circuit TV (CCTV) cameras will be installed as well as fiber optic drop cables to the cameras and existing traffic signals. Traffic signals will be timed to maintain coordinated traffic flow through the synchronized intersections. The progression of vehicles along the major roadway will be given priority even when the characteristics of the roadway traffic flow and control changes.