MIL- 10 MIL-008 Hopewell Road at Hamby Road Intersection Improvements Tier 1 Operation and Safety Improvements TSPLOST Milton Completed Operational improvements at the intersection and may include turn lanes, tr... more Operational improvements at the intersection and may include turn lanes, traffic signal or roundabout
CMES Barge Design Solutions August, 2020 February, 2018 November, 2021 October, 2021 https://cleargov.com/georgia/fulton/city/milton/projects/1228/hopewell-road-at-hamby-road-_-tsplost Sales Tax $2,420,000 $1,884,604 $535,396 Green Green Active kathy.stallard@miltonga.gov NULL 2026-02-27 09:04:04 NULL NULL NULL
MIL- 11 MIL-009 SR 140 at Green Road Intersection Improvements Tier 1 Operation and Safety Improvements TSPLOST Milton Land Operation improvements at the intersection that may include a traffic signa... more Operation improvements at the intersection that may include a traffic signal and interconnection to other signals on the SR 140 corridor
NULL Practical Design Partners January, 2027 April, 2021 July, 2028 July, 2028 https://cleargov.com/georgia/fulton/city/milton/projects/1213/sr-140-(arnold-mill-road)-at-green-road-_-tsplost Sales Tax $1,060,000 $63,400 $996,600 Green Green Active kathy.stallard@miltonga.gov NULL 2026-02-27 09:03:47 NULL NULL NULL
MIL- 12 MIL-012 Birmingham Road Middle Bridge Tier 1 Bridges TSPLOST Milton Land Bridge replacement with future trail accommodations NULL BM&K August, 2026 May, 2021 October, 2027 October, 2027 https://cleargov.com/georgia/fulton/city/milton/projects/1217/birmingham-road-middle-bridge-_-tsplost Sales Tax $2,803,458 $109,476 $2,693,982 Green Green Active kathy.stallard@miltonga.gov NULL 2026-02-27 09:03:33 NULL NULL NULL
MIL- 13 MIL-034 (Trail Planning) Multiple Pedestrian and Bike Improvements within the City Tier 1 Pedestrian and Bike Improvements TSPLOST Milton Completed Milton Trail Blueprint, Central Milton Trail, and Milton Community Trail Pr... more Milton Trail Blueprint, Central Milton Trail, and Milton Community Trail Prioritization Plan
N/A Kimley-Horn August, 2020 June, 2018 NULL July, 2020 https://www.cityofmiltonga.us/Home/ShowDocument?id=2859 Sales Tax $171,000 $171,000 $0 Green Green Active guest NULL 2021-09-30 18:34:16 NULL NULL NULL
MIL- 14 MIL-002 Bethany Road at Providence Road Intersection Improvements Tier 1 Operation and Safety Improvements TSPLOST Milton Bidding Operational improvements that will address the all way stop controlled inte... more Operational improvements that will address the all way stop controlled intersection and may include turn lanes, traffic signal or roundabout
NULL KCI February, 2026 April, 2021 November, 2027 November, 2027 https://cleargov.com/georgia/fulton/city/milton/projects/1194/bethany-road-at-providence-road-_-tsplost Sales Tax $2,200,000 $146,350 $2,053,650 Green Green Active kathy.stallard@miltonga.gov NULL 2026-02-27 09:06:53 NULL NULL NULL
MIL- 15 MIL-010 Freemanville Road at Redd Road Intersection Improvements Tier 1 Operation and Safety Improvements TSPLOST Milton Design Operational improvements at the intersection that may include turn lanes, t... more Operational improvements at the intersection that may include turn lanes, traffic signal, or roundabout
NULL KCI August, 2026 April, 2021 July, 2028 July, 2028 https://cleargov.com/georgia/fulton/city/milton/projects/1208/freemanville-road-at-redd-road-_-tsplost Sales Tax $1,020,000 $83,991 $936,009 Green Green Active kathy.stallard@miltonga.gov NULL 2026-02-27 09:08:02 NULL NULL NULL
MIL- 16 MIL-039 Paving Tier 3 Maintenance and Safety Enhancements TSPLOST Milton Planning Paving roadways in the City of Milton NULL NULL NULL NULL NULL NULL https://www.cityofmiltonga.us/home/showpublisheddocument/146/636970572854200000 Sales Tax $3,000,000 $0 $3,000,000 Gray Gray Active sara.leaders@cityofmiltonga.us NULL 2021-04-29 21:16:52 NULL NULL NULL
MIL- 17 MIL-037 Pedestrian Improvements Tier 2 Pedestrian and Bike Improvements TSPLOST Milton Planning Pedestrian Improvements NULL NULL NULL NULL NULL NULL https://www.cityofmiltonga.us/home/showpublisheddocument/144/636970572851530000 Sales Tax $2,100,000 $0 $2,100,000 Gray Gray Active sara.leaders@cityofmiltonga.us NULL 2021-04-29 21:17:22 NULL NULL NULL
MIL- 18 MIL-040 Quick Response Projects Tier 3 Quick Response TSPLOST Milton Planning Small traffic operations or safety improvement projects within the existing... more Small traffic operations or safety improvement projects within the existing right of way
NULL NULL NULL NULL NULL NULL https://www.cityofmiltonga.us/home/showpublisheddocument/148/636970572857130000 Sales Tax $775,160 $0 $775,160 Gray Gray Active sara.leaders@cityofmiltonga.us NULL 2021-04-29 21:15:52 NULL NULL NULL
MIL- 19 MIL-041 Bridge Repair and Replacement Tier 3 Bridges TSPLOST Milton Planning Bridge repair and replacement in the City of Milton NULL NULL NULL NULL NULL NULL https://www.cityofmiltonga.us/home/showpublisheddocument/150/636970572860100000 Sales Tax $791,865 $0 $791,865 Gray Gray Active sara.leaders@cityofmiltonga.us NULL 2021-04-29 21:15:31 NULL NULL NULL
MIL- 20 MIL-042 Pedestrian Improvements Tier 3 Pedestrian and Bike Improvements TSPLOST Milton Planning Pedestrian improvements in the City of Milton NULL NULL NULL NULL NULL NULL https://www.cityofmiltonga.us/home/showpublisheddocument/152/636970572863130000 Sales Tax $1,000,000 $0 $1,000,000 Gray Gray Active sara.leaders@cityofmiltonga.us NULL 2021-04-29 21:15:10 NULL NULL NULL
MIL- 21 MIL-031 (Interim) Morris Road at Webb Road Roundabout (Interim Improvement Before Widening) Tier 1 Operation and Safety Improvements TSPLOST Milton Completed The overall project description is for a proposed widening from Webb Road t... more The overall project description is for a proposed widening from Webb Road to Bethany Bend tying into McGinnis Ferry Road widening at Bethany Bend.
With recent signal improvements at Bethany Bend and Morris Road/McGinnis Ferry Road and upcoming interchange addition at GA 400 and McGinnis Ferry Road, an interim intersection improvement project was designed for the existing four way stop controlled intersection of Morris Road at Webb Road. Much of the project uses existing intersection footprint and converts the stop controlled intersection into a roundabout. The project will allow for future expansion with the upcoming widening project.
CMES BM&K March, 2018 January, 2018 October, 2018 October, 2018 https://cleargov.com/georgia/fulton/city/milton/projects/1212/morris-road-improvements-_-tsplost Sales Tax $400,000 $363,289 $36,711 Green Green Active sara.leaders@cityofmiltonga.us NULL 2021-04-29 21:48:52 NULL NULL NULL
MIL- 22 MIL-034 (Cogburn) Cogburn Road Sidewalks Tier 1 Pedestrian and Bike Improvements TSPLOST Milton Completed Sidewalks, curb and drainage improvements along both sides of Cogburn Road ... more Sidewalks, curb and drainage improvements along both sides of Cogburn Road from Bethany Bend to Oakstone Glen and Devonshire Farms
DAF Concrete Wolverton August, 2020 January, 2019 December, 2021 November, 2021 https://cleargov.com/georgia/fulton/city/milton/projects/1197/cogburn-road-sidewalks-_-tsplost Sales Tax $763,178 $635,579 $127,599 Green Green Active kathy.stallard@miltonga.gov NULL 2026-02-27 09:08:56 NULL NULL NULL
MIL- 23 NULL Cox Road Intersection Improvements Tier 1 Operation and Safety Improvements TSPLOST2 Milton Design Safety and Operational Improvements at several intersections along Cox Road NULL Pond and Company July, 2026 January, 2023 December, 2027 December, 2027 Sales Tax $6,000,000 $0 $6,000,000 Green Green Active kathy.stallard@miltonga.gov NULL 2026-02-27 09:10:08 Georgia City of Milton 2022-03-31
MIL- 24 NULL Intersection Efficiency Improvements Tier 1 Operation and Safety Improvements TSPLOST2 Milton Planning Intersection Efficiency Improvements - Various Locations
Webb at Cogburn -... more Intersection Efficiency Improvements - Various Locations
Webb at Cogburn - Turn Lane Improvements
NULL Pond and Company September, 2023 January, 2024 July, 2024 NULL Sales Tax $3,000,000 $0 $3,000,000 Green Green Active Robert.Dell-Ross@miltonga.gov NULL 2023-04-07 08:35:11 Georgia City of Milton 2022-03-31
MIL- 25 NULL Bike Accomodations Tier 1 Pedestrian and Bike Improvements TSPLOST2 Milton Planning Bike Accommodations - Location TBD NULL NULL NULL NULL NULL NULL Sales Tax $2,000,000 $0 $2,000,000 Green Green Active Robert.Dell-Ross@miltonga.gov NULL 2023-04-07 10:03:19 Georgia City of Milton 2022-03-31
MIL- 26 NULL Intersection Safety Improvements Tier 1 Operation and Safety Improvements TSPLOST2 Milton Planning Intersection Safety Improvments - Location TBD NULL NULL NULL NULL NULL NULL Sales Tax $3,000,000 $0 $3,000,000 Green Green Active Robert.Dell-Ross@miltonga.gov NULL 2022-10-10 17:28:47 Georgia City of Milton 2022-03-31
MIL- 27 NULL Pedestrian Enhancements/Streetscape Tier 1 Pedestrian and Bike Improvements TSPLOST2 Milton Planning Pedestrian Enhancements and Streetscape - Location TBD NULL NULL NULL NULL NULL NULL Sales Tax $1,000,000 $0 $1,000,000 Green Green Active Robert.Dell-Ross@miltonga.gov NULL 2023-04-07 10:26:42 Georgia City of Milton 2022-03-31
MIL- 28 NULL Community Trail Prioritization Tier 1 Pedestrian and Bike Improvements TSPLOST2 Milton Planning Community Trail Prioritization - Location TBD NULL NULL NULL NULL NULL NULL Sales Tax $3,000,000 $0 $3,000,000 Green Green Active Robert.Dell-Ross@miltonga.gov NULL 2022-10-10 17:39:48 Georgia City of Milton 2022-03-31
MIL- 29 NULL City Wide Tier 1 Bridges TSPLOST2 Milton Planning Bridges - Various Locations
Bridge Maintenance Prioritization NULL Pond and Company July, 2023 March, 2023 July, 2024 NULL Sales Tax $4,000,000 $0 $4,000,000 Green Green Active Robert.Dell-Ross@miltonga.gov NULL 2023-04-07 08:36:58 Georgia City of Milton 2022-03-31