TSPLOSTProjects

Project ID CSF- 74
Local ID OSI 620
Project Name Title Aldredge Road @Merk Road
Tier Tier 2
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST2
City City of South Fulton
Current Stage Design
Project Description improvements include three new turn lanes - a left on westbound Aldredge, and a right on eastbound Aldredge and a right on northbound Merk, a closed drainage system, 2.5-ft. curb & gutter, 2' stamped concrete, and 5 ft. sidewalks. Merk Road and Aldredge Road will be realigned to be a through street in the east-west direction and Merk Road from the south direction will be stop controlled.
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date February, 2027
Estimated Start Date For Project July, 2021
Estimated Construction Completion Date October, 2028
Estimated Substantial Completion Date October, 2030
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $207,130
TSPLOST Dollars Spent ($) $70,283
TSPLOST Dollars Committed (not spent) ($) $136,847
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year NULL
Last Update 2026-09-22 09:00:21