TSPLOSTProjects

Project ID CSF- 71
Local ID OSI 618
Project Name Title Welcome All Road @ Scarboro Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Design
Project Description The intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will address safety improvements, congestion mitigation, and geometric design standards.
Construction Firm Selected NULL
Design Firm Selected AEI
Estimated Design Completion Date May, 2023
Estimated Start Date For Project May, 2021
Estimated Construction Completion Date December, 2024
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,556,400
TSPLOST Dollars Spent ($) $84,643
TSPLOST Dollars Committed (not spent) ($) $1,471,757
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@fultoncountyga.gov
Project Year NULL
Last Update 2023-03-06 12:37:09
State NULL
Address NULL
Creation Date NULL