TSPLOSTProjects

Project ID CSF- 71
Local ID OSI 618
Project Name Title Welcome All Road @ Scarboro Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Bidding
Project Description The design project at Welcome All Road and Scarborough Road will include the addition of a circular single lane roundabout to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage with a typical section of 30-inch curb & gutter, streetlights, 2-ft of stamped concrete beauty strip, and 5' wide sidewalks. Streetlights will be added during construction
Construction Firm Selected NULL
Design Firm Selected AEI
Estimated Design Completion Date August, 2026
Estimated Start Date For Project May, 2021
Estimated Construction Completion Date July. 2027
Estimated Substantial Completion Date July. 2027
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $304,266
TSPLOST Dollars Spent ($) $195,192
TSPLOST Dollars Committed (not spent) ($) $109,074
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year NULL
Last Update 2026-09-22 08:46:47
State NULL
Address NULL
Creation Date NULL