| Project ID | CSF- 70 |
| Local ID | OSI 617 |
| Project Name Title | Welcome All Road @ Jailette Road |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | City of South Fulton |
| Current Stage | Bidding |
| Project Description | The design project at Welcome All Road and Jailette Road will realign the Stop regulated approach of Jailette Road to improve the angle of incidence at the intersection with Welcome All. Additional improvements include drainage, with a typical section of 30-inch curb & gutter, 2-ft of stamped concrete beauty strip, and 5' wide sidewalks. Streetlights will be added during construction. |
| Construction Firm Selected | NULL |
| Design Firm Selected | ATLAS |
| Estimated Design Completion Date | August, 2026 |
| Estimated Start Date For Project | May, 2021 |
| Estimated Construction Completion Date | July. 2027 |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $95,353 |
| TSPLOST Dollars Spent ($) | $75 |
| TSPLOST Dollars Committed (not spent) ($) | $95,278 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | roussan.francois@cityofsouthfultonga.gov |
| Project Year | 2020 |
| Last Update | 2026-09-22 08:44:29 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |