TSPLOSTProjects

Project ID CSF- 67
Local ID OSI 614
Project Name Title Rivertown Road @ Cedar Grove Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Completed
Project Description This construction project at Rivertown Road and Cedar Grove Road will build a single-lane roundabout to address a sharp angle intersection skew, congestion, and reduce the severity of accidents at this intersection. Additional improvements with this project include improving storm drainage with a typical section consisting of a 2-ft. curb & gutter, 2-ft. stamped concrete beauty strip, and 5-ft. wide sidewalks throughout the project limits. The extent of construction is approximately 1250 ft. along Rivertown Road and 600 ft. along Cedar Grove Road. Streetlights will also be added within the project limits.
Construction Firm Selected NULL
Design Firm Selected American Engineers, Inc
Estimated Design Completion Date December, 2023
Estimated Start Date For Project July, 2024
Estimated Construction Completion Date June, 2025
Estimated Substantial Completion Date June, 2025
Link To External Website https://performance.fultoncountyga.gov/stories/s/f85b-5vnc
Primary Funding Source Sales Tax
TSPLOST Budget ($) $2,806,821
TSPLOST Dollars Spent ($) $2,555,621
TSPLOST Dollars Committed (not spent) ($) $251,200
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year 2017
Last Update 2026-09-18 12:29:20
State NULL
Address NULL
Creation Date NULL