TSPLOSTProjects

Project ID CSF- 67
Local ID OSI 614
Project Name Title Rivertown Road @ Cedar Grove Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Bidding
Project Description Improvements will include the addition of a circular roundabout to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage, curb & gutter, streetlights, and 5' wide sidewalks.
Construction Firm Selected NULL
Design Firm Selected American Engineers, Inc
Estimated Design Completion Date February, 2023
Estimated Start Date For Project July, 2024
Estimated Construction Completion Date March, 2023
Estimated Substantial Completion Date NULL
Link To External Website https://performance.fultoncountyga.gov/stories/s/f85b-5vnc
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,310,000
TSPLOST Dollars Spent ($) $98,319
TSPLOST Dollars Committed (not spent) ($) $1,211,681
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@fultoncountyga.gov
Project Year 2017
Last Update 2023-03-05 00:49:10
State NULL
Address NULL
Creation Date NULL