TSPLOSTProjects

Project ID CSF- 61
Local ID OSI 607
Project Name Title Demooney Road @ West Stubbs Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Design
Project Description Intersection improvements will include the addition of a circular roundabout to address congestion and reduce the severity of accidents at this intersection. Additional improvements include drainage, curb & gutter, streetlights, and 5' wide sidewalks.
Construction Firm Selected NULL
Design Firm Selected AEI
Estimated Design Completion Date May, 2023
Estimated Start Date For Project December, 2020
Estimated Construction Completion Date November, 2024
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,422,000
TSPLOST Dollars Spent ($) $108,809
TSPLOST Dollars Committed (not spent) ($) $1,313,191
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@fultoncountyga.gov
Project Year 2021
Last Update 2023-03-05 00:38:41
State NULL
Address NULL