Project ID CSF- 61
Local ID OSI 607
Project Name Title Demooney Road @ West Stubbs Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Bidding
Project Description This design project at Demooney Road and West Stubbs Road will include the addition of a single lane roundabout to address congestion and reduce the severity of accidents at this 2-way Stop controlled intersection. Additional improvements include a closed drainage system, 2.5-ft. curb & gutter, 2' stamped concrete, and 5 ft. sidewalks. Streetlights will be added during construction.
Construction Firm Selected NULL
Design Firm Selected AEI
Estimated Design Completion Date August, 2026
Estimated Start Date For Project December, 2020
Estimated Construction Completion Date October, 2027
Estimated Substantial Completion Date October, 2027
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $187,298
TSPLOST Dollars Spent ($) $182,533
TSPLOST Dollars Committed (not spent) ($) $4,765
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year 2021
Last Update 2026-09-18 12:08:41
State NULL
Address NULL