| Project ID | CSF- 60 |
| Local ID | OSI 606 |
| Project Name Title | Cascade-Palmetto Highway @ West Stubbs Road |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | City of South Fulton |
| Current Stage | Completed |
| Project Description | The project and plans reflect the installation of a new signal at the intersection of Cascade Palmetto Highway and West Stubbs Road. In addition, it includes the installation of curb & gutter, a solar powered advanced signal warning sign, ADA ramps, and signing & marking. The existing non-signalized intersection already includes the necessary turn lanes and right of way. |
| Construction Firm Selected | NULL |
| Design Firm Selected | Not Applicable |
| Estimated Design Completion Date | Not Applicable |
| Estimated Start Date For Project | May, 2018 |
| Estimated Construction Completion Date | November, 2018 |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,554,000 |
| TSPLOST Dollars Spent ($) | $272,757 |
| TSPLOST Dollars Committed (not spent) ($) | $1,281,243 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | roussan.francois@fultoncountyga.gov |
| Project Year | 2019 |
| Last Update | 2021-05-03 22:46:16 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |