TSPLOSTProjects

Project ID CSF- 58
Local ID OSI 604
Project Name Title Campbellton Road @ Stonewall Tell Road (Project Design on Hold)
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Construction
Project Description Intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will provide geometric and congestion relief.
Construction Firm Selected CMC, INC
Design Firm Selected American Engineers, Inc
Estimated Design Completion Date December, 2022
Estimated Start Date For Project April, 2020
Estimated Construction Completion Date March, 2024
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,422,000
TSPLOST Dollars Spent ($) $172,932
TSPLOST Dollars Committed (not spent) ($) $1,249,068
Cost Status Red
Schedule Status Green
Status Active
Editor roussan.francois@fultoncountyga.gov
Project Year 2017
Last Update 2023-03-05 00:40:45
State NULL
Address NULL
Creation Date NULL