TSPLOSTProjects

Project ID CSF- 58
Local ID OSI 604
Project Name Title Campbellton Road @ Stonewall Tell Road (Project Design on Hold)
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Completed
Project Description This completed construction project included a realignment of the intersection from a skewed intersection with a stop condition to standard 4-way intersection with a new traffic signal. Additional improvements included adding turning lanes in each direction along Campbellton Road and Stonewall Tell Road, installation of 5-feet sidewalks, curb and gutter, improved stormwater drainage, 2-feet stamp concrete, and installation of streetlights within the project limits.
Construction Firm Selected CMC, INC
Design Firm Selected American Engineers, Inc
Estimated Design Completion Date December, 2022
Estimated Start Date For Project April, 2020
Estimated Construction Completion Date March, 2024
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $3,386,248
TSPLOST Dollars Spent ($) $3,386,248
TSPLOST Dollars Committed (not spent) ($) $0
Cost Status Red
Schedule Status Green
Status Active