TSPLOSTProjects

Project ID CSF- 57
Local ID OSI 603
Project Name Title Butner Road @ Pittman Road
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Design
Project Description The design project on Burner Road will improve traffic safety by realigning the approach of Pittman Road to eliminate an extreme angle of incidence at the intersection through the use of a roundabout. Additional improvements include a closed drainage system, 2.5-ft. curb & gutter, 2' stamped concrete, and 5 ft. sidewalks. Streetlights will be added during construction.
Construction Firm Selected NULL
Design Firm Selected AEI
Estimated Design Completion Date March, 2027
Estimated Start Date For Project December, 2020
Estimated Construction Completion Date July, 2029
Estimated Substantial Completion Date July, 2029
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $143,672
TSPLOST Dollars Spent ($) $83,680
TSPLOST Dollars Committed (not spent) ($) $59,992
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year 2020
Last Update 2026-09-18 11:38:58
State NULL
Address NULL
Creation Date NULL