| Project ID | CSF- 56 |
| Local ID | OSI 602 |
| Project Name Title | Butner Road @ Union Road |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | City of South Fulton |
| Current Stage | Design |
| Project Description | Intersection improvements will include the use of an oval roundabout or circular roundabout. A traffic report concluded that a roundabout is the best alternative to handle the traffic congestion at this intersection. Additional improvements include drainage, curb & gutter, street lights, and sidewalks. |
| Construction Firm Selected | NULL |
| Design Firm Selected | American Engineers, Inc |
| Estimated Design Completion Date | December, 2022 |
| Estimated Start Date For Project | December, 2019 |
| Estimated Construction Completion Date | August, 2024 |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | https://performance.fultoncountyga.gov/stories/s/v555-6sca |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,986,000 |
| TSPLOST Dollars Spent ($) | $241,500 |
| TSPLOST Dollars Committed (not spent) ($) | $1,744,500 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | roussan.francois@fultoncountyga.gov |
| Project Year | 2017 |
| Last Update | 2023-03-05 00:28:01 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |