| Project ID | CSF- 55 |
| Local ID | OSI 601 |
| Project Name Title | Butner Road @ Camp Creek Parkway |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | City of South Fulton |
| Current Stage | Design |
| Project Description | The proposed Butner Road project is a capacity project that begins at the intersection of Camp Creek Parkway and extends approximately 1,000 feet to the north along Butner Road. It consists of widening the existing Butner Road by adding left and right-turn lanes, providing a nature trail at-grade crossing and updating the intersection signalization and guardrails, as a safety measure, on the east side of Butner Road to Merk Road. The travel lanes will be minimum 11 foot-wide with 2-foot stamped concrete and 12-foot trail on the east side. This project also includes signal upgrade and installation of new decorative mast arms. |
| Construction Firm Selected | NULL |
| Design Firm Selected | American Engineers, Inc |
| Estimated Design Completion Date | December, 2022 |
| Estimated Start Date For Project | August, 2020 |
| Estimated Construction Completion Date | January, 2025 |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $3,174,000 |
| TSPLOST Dollars Spent ($) | $16,250 |
| TSPLOST Dollars Committed (not spent) ($) | $3,157,750 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | roussan.francois@fultoncountyga.gov |
| Project Year | 2017 |
| Last Update | 2023-03-05 00:26:37 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |