TSPLOSTProjects

Project ID CSF- 54
Local ID B 502
Project Name Title Bethsaida over Morning Creek
Tier Tier 2
Project Type Bridges
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Construction
Project Description Bridge replacement to be analyzed for a better rating capacity and alleviate congestion.
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date NULL
Estimated Start Date For Project NULL
Estimated Construction Completion Date April, 2028
Estimated Substantial Completion Date April, 2028
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $0
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $0
Cost Status Gray
Schedule Status Gray
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year NULL
Last Update 2026-09-17 09:48:38
State NULL
Address NULL
Creation Date NULL