TSPLOSTProjects

Project ID CSF- 53
Local ID B 501
Project Name Title Enon Road over Camp Creek Tributary (Timber Bridge)
Tier Tier 1
Project Type Bridges
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Design
Project Description The proposed project will replace the existing culvert located on Enon Road between Enon Mill Drive and Enon Pines Drive. The deteriorated timber culvert will be removed and replaced with a structure to carry two 12-foot travel lanes and 8-foot shoulders, which include 6-foot sidewalks.
Construction Firm Selected NULL
Design Firm Selected AEI
Estimated Design Completion Date February, 2022
Estimated Start Date For Project December, 2022
Estimated Construction Completion Date February, 2024
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $600,000
TSPLOST Dollars Spent ($) $87,454
TSPLOST Dollars Committed (not spent) ($) $512,546
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@fultoncountyga.gov
Project Year 2020
Last Update 2023-03-05 00:22:05
State NULL
Address NULL
Creation Date NULL