TSPLOSTProjects

Project ID CSF- 50
Local ID RS 405
Project Name Title Woodward Estates
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Completed
Project Description The roads (Amethist Court, Garnett Way, Mica Trace, Old Rocky Road, Rockway Road, Rocky Court, Topaz Trail, Turquoise Trail, and Woodward Road) within the subdivision to be resurfaced may have either existing concrete curb and gutter sections or will be flush with the shoulder of the road. The work will include all necessary preparation work (e.g., full depth patching, milling, and single surface treatment). The roads will then be resurfaced in a manner that will provide uniformity of the asphalt. After resurfacing, all existing pavement markings such as line striping will be reinstalled.
Construction Firm Selected CWM
Design Firm Selected Not Applicable
Estimated Design Completion Date Not Applicable
Estimated Start Date For Project NULL
Estimated Construction Completion Date June, 2019
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $469,318
TSPLOST Dollars Spent ($) $294,440
TSPLOST Dollars Committed (not spent) ($) $174,878
Cost Status Green
Schedule Status Green
Status Active
Editor roussan.francois@fultoncountyga.gov
Project Year 2018
Last Update 2021-05-03 20:29:52
State NULL
Address NULL
Creation Date NULL