TSPLOSTProjects

Project ID HA- 6
Local ID HA-108
Project Name Title Hapeville Paving Project
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City Hapeville
Current Stage Bidding
Project Description Paving of roads
Construction Firm Selected TBD
Design Firm Selected Keck & Wood
Estimated Design Completion Date August, 2021
Estimated Start Date For Project January, 2022
Estimated Construction Completion Date April, 2022
Estimated Substantial Completion Date March, 2022
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $600,000
TSPLOST Dollars Spent ($) $1,360,567
TSPLOST Dollars Committed (not spent) ($) $-760,567
Cost Status NULL
Schedule Status Gray
Status Active
Editor lsudduth@hapeville.org
Project Year 2021
Last Update 2021-11-09 21:59:59
State NULL
Address NULL
Creation Date NULL