Project ID CSF- 208
Local ID QRP 1106
Project Name Title Mallory Walk Subdivision
Tier Tier 1
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Completed
Project Description Subdivision Resurfacing
Construction Firm Selected CW Matthews
Design Firm Selected NULL
Estimated Design Completion Date NULL
Estimated Start Date For Project NULL
Estimated Construction Completion Date June, 2021
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $114,142
TSPLOST Dollars Spent ($) $114,142
TSPLOST Dollars Committed (not spent) ($) $0
Cost Status NULL
Schedule Status NULL
Status Active
Editor roussan.francois@fultoncountyga.gov
Project Year 2021
Last Update 2021-10-12 20:06:18