Project ID FA- 26
Local ID NULL
Project Name Title Milo Fisher, Bay Street & Grant Street Pedestrian Improvements
Tier Tier 2
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City Fairburn
Current Stage Completed
Project Description Extend sidewalk on Milo Fisher to the intersection of Clayton Street, extend sidewalk on Bay Street to the intersection of Malone Street, install sidewalk on Grant street from Milo Fisher Street to Chestnut Street.
Construction Firm Selected BOSS Concrete Construction, LLC
Design Firm Selected NULL
Estimated Design Completion Date March, 2021
Estimated Start Date For Project April, 2021
Estimated Construction Completion Date June, 2021
Estimated Substantial Completion Date May, 2021
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $25,000
TSPLOST Dollars Spent ($) $19,977
TSPLOST Dollars Committed (not spent) ($) $5,023
Cost Status Green
Schedule Status Green
Status Active
Editor lthompson@fairburn.com
Project Year 2021
Last Update 2021-09-09 11:55:01