| Project ID | CSF- 199 |
| Local ID | NULL |
| Project Name Title | TSPLOST CEI Services- 2021 |
| Tier | Tier 1 |
| Project Type | Project Management |
| Initiatve Type | TSPLOST |
| City | City of South Fulton |
| Current Stage | Design |
| Project Description | PM |
| Construction Firm Selected | NULL |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | NULL |
| Estimated Start Date For Project | NULL |
| Estimated Construction Completion Date | December, 2021 |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $321,725 |
| TSPLOST Dollars Spent ($) | $321,725 |
| TSPLOST Dollars Committed (not spent) ($) | $0 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | roussan.francois@fultoncountyga.gov |
| Project Year | 2020 |
| Last Update | 2021-02-27 01:18:26 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |