| Project ID | EP- 27 |
| Local ID | EP-130 |
| Project Name Title | Willingham Drive |
| Tier | Tier 1 |
| Project Type | Maintenance and Safety Enhancements |
| Initiatve Type | TSPLOST |
| City | East Point |
| Current Stage | Completed |
| Project Description | Roadway resurfacing and Safety |
| Construction Firm Selected | Mullins Brother's Paving |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | April, 2017 |
| Estimated Start Date For Project | September, 2017 |
| Estimated Construction Completion Date | September, 2017 |
| Estimated Substantial Completion Date | December, 2019 |
| Link To External Website | |
| Primary Funding Source | TSPLOST |
| TSPLOST Budget ($) | $651,000 |
| TSPLOST Dollars Spent ($) | $651,000 |
| TSPLOST Dollars Committed (not spent) ($) | $0 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | guest |
| Project Year | 2017 |
| Last Update | 2021-05-05 00:48:38 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |