TSPLOSTProjects

Project ID MIL- 22
Local ID MIL-034 (Cogburn)
Project Name Title Cogburn Road Sidewalks
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City Milton
Current Stage Completed
Project Description Sidewalks, curb and drainage improvements along both sides of Cogburn Road from Bethany Bend to Oakstone Glen and Devonshire Farms
Construction Firm Selected DAF Concrete
Design Firm Selected Wolverton
Estimated Design Completion Date August, 2020
Estimated Start Date For Project January, 2019
Estimated Construction Completion Date December, 2021
Estimated Substantial Completion Date November, 2021
Link To External Website https://cleargov.com/georgia/fulton/city/milton/projects/1197/cogburn-road-sidewalks-_-tsplost
Primary Funding Source Sales Tax
TSPLOST Budget ($) $763,178
TSPLOST Dollars Spent ($) $635,579
TSPLOST Dollars Committed (not spent) ($) $127,599
Cost Status Green
Schedule Status Green
Status Active
Editor kathy.stallard@miltonga.gov
Project Year NULL
Last Update 2026-02-27 09:08:56
State NULL
Address NULL
Creation Date NULL