TSPLOSTProjects

Project ID CP- 30
Local ID CP-101
Project Name Title Maintenance and Safety Enhancements
Tier Tier 2
Project Type Maintenance and Safety Enhancements
Initiatve Type TSPLOST
City College Park
Current Stage Completed
Project Description TSplost resurfacing Project is now completed
Construction Firm Selected Mullins Brother Paving
Design Firm Selected NULL
Estimated Design Completion Date September, 2019
Estimated Start Date For Project September, 2019
Estimated Construction Completion Date April, 2020
Estimated Substantial Completion Date April, 2020
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $716,447
TSPLOST Dollars Spent ($) $246,072
TSPLOST Dollars Committed (not spent) ($) $470,375
Cost Status Green
Schedule Status Green
Status Active
Editor rcotton@collegeparkga.com
Project Year 2019
Last Update 2020-11-19 20:16:10
State NULL
Address NULL
Creation Date NULL