| Project ID | CP- 30 |
| Local ID | CP-101 |
| Project Name Title | Maintenance and Safety Enhancements |
| Tier | Tier 2 |
| Project Type | Maintenance and Safety Enhancements |
| Initiatve Type | TSPLOST |
| City | College Park |
| Current Stage | Completed |
| Project Description | TSplost resurfacing Project is now completed |
| Construction Firm Selected | Mullins Brother Paving |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | September, 2019 |
| Estimated Start Date For Project | September, 2019 |
| Estimated Construction Completion Date | April, 2020 |
| Estimated Substantial Completion Date | April, 2020 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $716,447 |
| TSPLOST Dollars Spent ($) | $246,072 |
| TSPLOST Dollars Committed (not spent) ($) | $470,375 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | rcotton@collegeparkga.com |
| Project Year | 2019 |
| Last Update | 2020-11-19 20:16:10 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |