TSPLOSTProjects

Project ID ALP- 35
Local ID C1934
Project Name Title WINDWARD PARKWAY EASTBOUND WIDENING - WESTSIDE PARKWAY TO NORTH POINT PARKWAY
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Alpharetta
Current Stage Construction
Project Description This is one of two projects which evolved from the conceptual design work comprising the "Windward Parkway Business District/Union Hill Road Capacity Improvements - TSPLOST Project". The project limits are from Westside Parkway to North Point Parkway. Improvements will include: (1) The installation of a third travel lane from Westside Parkway to the southbound Georgia 400 on-ramp. All travel lanes will be 11'' wide. (2) The installation of a 4'' bike lane. (3) The installation of a 6'' wide sidewalk. The typical section will seek to match that of the "Windward Parkway Triple Left-Turn Lane at Georgia 400 Interchange" project. On Monday, May 6, 2019 design of the project was awarded to Tetra Tech, Inc. in the amount of $302,830.00. Design is complete. Bids were received on Thursday, May 14, 2020. Project was awarded to Sol Construction, LLC by City Council on Monday, June 15, 2020. The Notice to Proceed was issued August 8, 2020 and the project duration is anticipated to be 365 days.
Construction Firm Selected Sol Construction LLC
Design Firm Selected Tetra Tech, Inc.
Estimated Design Completion Date February, 2020
Estimated Start Date For Project NULL
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website http://alpharetta.maps.arcgis.com/apps/MapJournal/index.html?appid=c2930590bb57457b908c8d9ec82caba0§ion=38
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,639,117
TSPLOST Dollars Spent ($) $1,275,417
TSPLOST Dollars Committed (not spent) ($) $363,700
Cost Status Green
Schedule Status Yellow
Status Active
Editor psewczwicz@alpharetta.ga.us
Project Year NULL
Last Update 2021-10-12 12:56:26
State NULL
Address NULL
Creation Date NULL