| Project ID | JCR- 25 |
| Local ID | JCR-020 |
| Project Name Title | Medlock Bridge Road at State Bridge Improvements - Phase 1 |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Johns Creek |
| Current Stage | Completed |
| Project Description | This project will make improvements to the intersection of Medlock Bridge and State Bridge Road. Proposed improvements are adding a third southbound lane on SR 141/Medlock Bridge Road and a third eastbound and westbound lane on State Bridge Road. This will be accomplished using a combination of widening and restriping to minimize impacts. |
| Construction Firm Selected | Vertical Earth |
| Design Firm Selected | WSP |
| Estimated Design Completion Date | June, 2020 |
| Estimated Start Date For Project | September, 2020 |
| Estimated Construction Completion Date | July, 2021 |
| Estimated Substantial Completion Date | June, 2021 |
| Link To External Website | https://www.johnscreekga.gov/Residents/Public-Works/TSPLOST/Medlock-Bridge-Rd-at-State-Bridge-Rd |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $2,205,757 |
| TSPLOST Dollars Spent ($) | $2,205,757 |
| TSPLOST Dollars Committed (not spent) ($) | $0 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Inactive |
| Editor | chris.haggard@johnscreekga.gov |
| Project Year | 2021 |
| Last Update | 2022-08-22 15:03:34 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |