TSPLOSTProjects

Project ID ALP- 32
Local ID C1714
Project Name Title BETHANY ROAD AT MID-BROADWELL ROAD INTERSECTION IMPROVEMENTS
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Alpharetta
Current Stage Completed
Project Description This project involves intersection operational improvements incorporating a roundabout at the intersection of Bethany Road and Mid Broadwell Road. The City has received numerous complaints regarding left turns onto Mid Broadwell Road from motorists traveling south on Bethany Road and from residents of Pindell Glen Subdivision trying to leave their subdivision. Residents have complained about the speed of vehicles on Mid Broadwell Road and have requested a reduction of the speed limit or the installation of a traffic signal or four-way stop. As these options do not meet warrants, a roundabout is proposed to reduce speeds in the area and assist in left-turn movements. The preliminary cost estimate for this project was $1.28 million with funding provided through T-SPLOST (transportation special purpose local option sales tax). The design of this project was awarded to Tetra Tech, Inc. in the amount of $131,170 by City Council on December 12, 2016. The conceptual design for this project was presented to City Council on June 5, 2017.
Construction Firm Selected CMES, Inc.
Design Firm Selected Tetra Tech, Inc.
Estimated Design Completion Date January, 2018
Estimated Start Date For Project NULL
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website http://alpharetta.maps.arcgis.com/apps/MapJournal/index.html?appid=c2930590bb57457b908c8d9ec82caba0§ion=38
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,368,453
TSPLOST Dollars Spent ($) $1,368,302
TSPLOST Dollars Committed (not spent) ($) $151
Cost Status Green
Schedule Status Red
Status Active
Editor psewczwicz@alpharetta.ga.us
Project Year NULL
Last Update 2021-10-12 13:54:18
State NULL
Address NULL
Creation Date NULL