| Project ID | CSF- 184 |
| Local ID | NULL |
| Project Name Title | Pedestrian/Bike/Landscape/Streetscape Projects |
| Tier | Tier 1 |
| Project Type | Pedestrian and Bike Improvements |
| Initiatve Type | TSPLOST |
| City | City of South Fulton |
| Current Stage | Completed |
| Project Description | This completed construction project added 0.50 mi of 5-feet wide concrete ADA (Americans with Disabilities Act) compliant sidewalks along both sides of Danforth Road from Cascade Road to Rehoboth Circle for approximately 0.715 miles. Additional improvements included curb and gutter and associated storm water structures, a two-foot-wide stamped concrete strip at the back of the curb, and pedestrian street lighting. |
| Construction Firm Selected | NULL |
| Design Firm Selected | NULL |
| Estimated Design Completion Date | March, 2027 |
| Estimated Start Date For Project | March, 2027 |
| Estimated Construction Completion Date | NULL |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,411,181 |
| TSPLOST Dollars Spent ($) | $1,470,487 |
| TSPLOST Dollars Committed (not spent) ($) | $-59,306 |
| Cost Status | Gray |
| Schedule Status | Gray |
| Status | Active |
| Editor | roussan.francois@cityofsouthfultonga.gov |
| Project Year | NULL |
| Last Update | 2026-09-17 09:56:39 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |