Project ID CSF- 184
Local ID NULL
Project Name Title Pedestrian/Bike/Landscape/Streetscape Projects
Tier Tier 1
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City City of South Fulton
Current Stage Completed
Project Description This completed construction project added 0.50 mi of 5-feet wide concrete ADA (Americans with Disabilities Act) compliant sidewalks along both sides of Danforth Road from Cascade Road to Rehoboth Circle for approximately 0.715 miles. Additional improvements included curb and gutter and associated storm water structures, a two-foot-wide stamped concrete strip at the back of the curb, and pedestrian street lighting.
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date March, 2027
Estimated Start Date For Project March, 2027
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $1,411,181
TSPLOST Dollars Spent ($) $1,470,487
TSPLOST Dollars Committed (not spent) ($) $-59,306
Cost Status Gray
Schedule Status Gray
Status Active
Editor roussan.francois@cityofsouthfultonga.gov
Project Year NULL
Last Update 2026-09-17 09:56:39
State NULL
Address NULL