| Project ID | FIB- 25 |
| Local ID | OSI 612 |
| Project Name Title | Fulton Industrial Boulevard @ Cascade Road |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Fulton Industrial Blvd. |
| Current Stage | Design |
| Project Description | Intersection will be analyzed for traffic improvements including a roundabout alternative. Curb & Gutter, drainage, sidewalks, and street lights will be part of the proposed improvements. The intersection improvements will provide geometric and congestion relief. |
| Construction Firm Selected | TBD |
| Design Firm Selected | Kimley-Horn |
| Estimated Design Completion Date | December, 2020 |
| Estimated Start Date For Project | July, 2019 |
| Estimated Construction Completion Date | December, 2023 |
| Estimated Substantial Completion Date | October, 2023 |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $1,000,000 |
| TSPLOST Dollars Spent ($) | $100,000 |
| TSPLOST Dollars Committed (not spent) ($) | $900,000 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | cordell.rhymer@fultoncountyga.gov |
| Project Year | 2019 |
| Last Update | NULL |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |