TSPLOSTProjects

Project ID JCR- 11
Local ID JCR-013
Project Name Title State Bridge Widening (Kimball Bridge to Medlock Bridge)
Tier Tier 2
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Johns Creek
Current Stage Planning
Project Description This project will widen State Bridge Road from 4 to 6 lanes between Kimball Bridge and Medlock Bridge and may include improvements such as sidewalks, trails and landscaping.
Construction Firm Selected Vertical Earth
Design Firm Selected WSP USA INC.
Estimated Design Completion Date June, 2020
Estimated Start Date For Project September, 2020
Estimated Construction Completion Date July, 2021
Estimated Substantial Completion Date June, 2021
Link To External Website https://www.johnscreekga.gov/Residents/Public-Works/TSPLOST/Medlock-Bridge-Rd-at-State-Bridge-Rd
Primary Funding Source Sales Tax
TSPLOST Budget ($) $2,205,757
TSPLOST Dollars Spent ($) $2,205,757
TSPLOST Dollars Committed (not spent) ($) $0
Cost Status Green
Schedule Status Green
Status Inactive
Editor kevin.albi@johnscreekga.gov
Project Year 2021
Last Update 2024-07-08 14:49:25
State Georgia
Address City of Johns Creek
Creation Date NULL