TSPLOSTProjects

Project ID JCR- 9
Local ID JCR-009
Project Name Title Barnwell Road at Holcomb Bridge Road Intersection Improvements
Tier Tier 1
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Johns Creek
Current Stage Construction
Project Description This project includes dual left turn lanes, a through lane, and a right-turn lane on Barnwell Road at SR 140/Holcomb Bridge Road. This project may include improvements including bike lanes, sidewalks, trails, landscaping and a pedestrian bridge over Hogan's Creek.
Construction Firm Selected CW Matthews
Design Firm Selected DPE
Estimated Design Completion Date December, 2019
Estimated Start Date For Project May, 2021
Estimated Construction Completion Date July, 2023
Estimated Substantial Completion Date June, 2023
Link To External Website https://www.johnscreekga.gov/Residents/Public-Works/TSPLOST/Barnwell-Rd-at-Holcomb-Bridge-Rd-Intersection-Impr
Primary Funding Source Federal/State and Local
TSPLOST Budget ($) $2,500,000
TSPLOST Dollars Spent ($) $1,674,213
TSPLOST Dollars Committed (not spent) ($) $825,787
Cost Status Green
Schedule Status Green
Status Active
Editor chris.haggard@johnscreekga.gov
Project Year NULL
Last Update 2022-08-22 15:09:25
State NULL
Address NULL
Creation Date NULL