| Project ID | JCR- 9 |
| Local ID | JCR-009 |
| Project Name Title | Barnwell Road at Holcomb Bridge Road Intersection Improvements |
| Tier | Tier 1 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Johns Creek |
| Current Stage | Construction |
| Project Description | This project includes dual left turn lanes, a through lane, and a right-turn lane on Barnwell Road at SR 140/Holcomb Bridge Road. This project may include improvements including bike lanes, sidewalks, trails, landscaping and a pedestrian bridge over Hogan's Creek. |
| Construction Firm Selected | CW Matthews |
| Design Firm Selected | DPE |
| Estimated Design Completion Date | December, 2019 |
| Estimated Start Date For Project | May, 2021 |
| Estimated Construction Completion Date | July, 2023 |
| Estimated Substantial Completion Date | June, 2023 |
| Link To External Website | https://www.johnscreekga.gov/Residents/Public-Works/TSPLOST/Barnwell-Rd-at-Holcomb-Bridge-Rd-Intersection-Impr |
| Primary Funding Source | Federal/State and Local |
| TSPLOST Budget ($) | $2,500,000 |
| TSPLOST Dollars Spent ($) | $1,674,213 |
| TSPLOST Dollars Committed (not spent) ($) | $825,787 |
| Cost Status | Green |
| Schedule Status | Green |
| Status | Active |
| Editor | chris.haggard@johnscreekga.gov |
| Project Year | NULL |
| Last Update | 2022-08-22 15:09:25 |
| State | NULL |
| Address | NULL |
| Creation Date | NULL |