TSPLOSTProjects

Project ID JCR- 7
Local ID JCR-004
Project Name Title McGinnis Ferry Road Widening from Union Hill to Sargent Rd
Tier Tier 1
Project Type Congestion Relief
Initiatve Type TSPLOST
City Johns Creek
Current Stage Land
Project Description This regional capacity enhancement project includes widening of McGinnis Ferry Road from 2-lanes to 4-lanes. The project is jointly funded by GDOT, Forsyth County, Alpharetta and Johns Creek. McGinnis Ferry Road is a major east/ west corridor connecting I-85 with GA 400. The project limits are from Seven Oaks Parkway/Brassfield Drive to Douglas Road.
Construction Firm Selected NULL
Design Firm Selected Moreland Altobelli
Estimated Design Completion Date December, 2020
Estimated Start Date For Project December, 2022
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website https://www.johnscreekga.gov/Residents/Public-Works/TSPLOST/McGinnis-Ferry-Road-Widening
Primary Funding Source Federal/State and Local
TSPLOST Budget ($) $7,500,000
TSPLOST Dollars Spent ($) $1,995,280
TSPLOST Dollars Committed (not spent) ($) $5,504,720
Cost Status Green
Schedule Status Green
Status Active
Editor chris.haggard@johnscreekga.gov
Project Year NULL
Last Update 2022-01-11 15:17:30
State NULL
Address NULL
Creation Date NULL