TSPLOSTProjects

Project ID JCR- 6
Local ID JCR-003
Project Name Title Jones Bridge Widening (Ph.1 - Waters to Buice; Ph. 2 - Buice to State Bridge)
Tier Tier 1
Project Type Congestion Relief
Initiatve Type TSPLOST
City Johns Creek
Current Stage Completed
Project Description This project will widen Jones Bridge Road from 2 to 4 lanes between Waters Road and State Bridge Road and may include improvements such as sidewalks, trails and landscaping. Phase 1 will include improvements between Waters Road to Buice Road. Phase 2 will include improvements between Buice Road to State Bridge Road
Construction Firm Selected CMES, Inc.
Design Firm Selected Kimley Horn Engineering
Estimated Design Completion Date May, 2021
Estimated Start Date For Project June, 2023
Estimated Construction Completion Date June, 2025
Estimated Substantial Completion Date June, 2025
Link To External Website https://www.johnscreekga.gov/Residents/Public-Works/TSPLOST/Jones-Bridge-Rd-Widening-(Waters-to-Buice;-Buice-t
Primary Funding Source Sales Tax
TSPLOST Budget ($) $11,000,000
TSPLOST Dollars Spent ($) $22,647,680
TSPLOST Dollars Committed (not spent) ($) $-11,647,680
Cost Status Red
Schedule Status Green
Status Inactive
Editor brian.oconnor@johnscreekga.gov
Project Year 2023
Last Update 2026-08-17 16:58:27
State NULL
Address NULL
Creation Date NULL