TSPLOSTProjects

Project ID UC- 23
Local ID UC-307
Project Name Title Pedestrian/Bike/Landscape/Streetscape Projects
Tier Tier 3
Project Type Pedestrian and Bike Improvements
Initiatve Type TSPLOST
City Union City
Current Stage Design
Project Description Pedestrian/Bike Improvements in Union City - Roosevelt Hwy (US29) (Lower Dixie Lake Road to Stonewall Tell Road)
Construction Firm Selected TBD
Design Firm Selected Atlas
Estimated Design Completion Date April, 2021
Estimated Start Date For Project July, 2021
Estimated Construction Completion Date November, 2020
Estimated Substantial Completion Date December, 2021
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $496,069
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $496,069
Cost Status Green
Schedule Status Green
Status Active
Editor lferguson@unioncityga.org
Project Year 2021
Last Update 2021-02-02 19:59:33
State NULL
Address NULL
Creation Date NULL