| Project ID | FA- 20 |
| Local ID | NULL |
| Project Name Title | Quiet Zone R/R Crossings Project |
| Tier | Tier 2 |
| Project Type | Operation and Safety Improvements |
| Initiatve Type | TSPLOST |
| City | Fairburn |
| Current Stage | Planning |
| Project Description | Quiet Zone Railroad Crossings Project Authorized a Task Order with Pond & Company for Quiet Zone Evaluation and Report on December 16, 2025. Quiet Zone Support Agreement with CSX for $25,300.00 executed on October 7, 2025. Quiet Zone Field Diagnostic conducted on February 6, 2026. |
| Construction Firm Selected | NULL |
| Design Firm Selected | Pond & Company |
| Estimated Design Completion Date | NULL |
| Estimated Start Date For Project | NULL |
| Estimated Construction Completion Date | NULL |
| Estimated Substantial Completion Date | NULL |
| Link To External Website | |
| Primary Funding Source | Sales Tax |
| TSPLOST Budget ($) | $750,000 |
| TSPLOST Dollars Spent ($) | $0 |
| TSPLOST Dollars Committed (not spent) ($) | $750,000 |
| Cost Status | Gray |
| Schedule Status | Gray |
| Status | Active |
| Editor | lthompson@fairburn.com |
| Project Year | 2020 |
| Last Update | 2026-08-31 10:13:22 |