TSPLOSTProjects

Project ID FA- 20
Local ID NULL
Project Name Title Quiet Zone R/R Crossings Project
Tier Tier 2
Project Type Operation and Safety Improvements
Initiatve Type TSPLOST
City Fairburn
Current Stage Planning
Project Description Quiet Zone Railroad Crossings Project
Construction Firm Selected NULL
Design Firm Selected NULL
Estimated Design Completion Date NULL
Estimated Start Date For Project NULL
Estimated Construction Completion Date NULL
Estimated Substantial Completion Date NULL
Link To External Website
Primary Funding Source Sales Tax
TSPLOST Budget ($) $750,000
TSPLOST Dollars Spent ($) $0
TSPLOST Dollars Committed (not spent) ($) $750,000
Cost Status Gray
Schedule Status Gray
Status Active
Editor lthompson@fairburn.com
Project Year 2020
Last Update NULL
State NULL
Address NULL
Creation Date NULL